HomeMy WebLinkAbout3452•
ORDINANCE NO. 3452
AN ORDINANCE of the City of Port Angeles, Washington, relating to
electricity services and charges making changes to Chapter 13.12 of
Title 13 of the Port Angeles Municipal Code.
THE CITY COUNCIL OF THE CITY OF PORT ANGELES DO HEREBY ORDAIN
AS FOLLOWS:
Section 1. Ordinances 2054 as amended, and Title 13 of the Port Angeles
Municipal Code Chapter 13.12 is amended to read as follows:
CHAPTER 13.12 - ELECTRICITY — SERVICES AND CHARGES
13.12.010 - General provisions applicable to all services.
13.12.015 - Time of use electric rate
13.12.020 - Uniform electric rate.
13.12.021 - Point of delivery.
13.12.025 - Rate Class assignment.
13.12.030 - Schedule R -03- Residential service.
13.12.031 - Schedule R -03- Residential service time of use rate.
13.12.040 - Schedule GS- 03- General service.
13.12.0401.Schedule GS- 03- General service time of use rate.
13.12.041 - Schedule GD- 03- General service demand.
13.12.0411.Schedule GD- 03- General service demand time of use rate.
13.12.042 - Schedule NP- 03- Nonprofit tax - deductible.
13.12.0421. Schedule NP- 03- Nonprofit tax - deductible time of use rate.
13.12.043 - Schedule GD- 04- General service demand - primary metered.
13.12.044 - Schedule GD- 04- General service demand - primary metered time of use
rate.
13.12.060 - Schedule PS -03- Primary service.
13.12.061 - Schedule PS -03- Primary service time of use rate.
13.12.071 - Schedule IT- 03- Industrial transmission.
13.12.072 - Schedule L- 03- Lighting.
13.12.073 - Schedule MW -03- Municipal water pumping.
13.12.074 - New or expanded loads.
13.12.075 - Schedule MW -03- Municipal water pumping time of use rate.
•
13.12.080 - Contract sales and purchases.
13.12.100 - Electrical work permits and fees.
13.12.110 - Contract and administration charge.
13.12.015 — Time of use electric rate.
After City Council formally accepts the Advanced Metering Infrastructure System, the monthly
rate for electricity consumed shall be in accordance with Sections 13.12.031, 13.12.0401,
13.12.0411., 13.12.0421., 13.12.044, 13.12.061, and 13.12.075. The monthly rate includes all
applicable taxes.
13.12.020 - Uniform electric rate.
Before the City Council formally accepts the Advanced Metering Infrastructure System, Tthe
monthly rate for electricity consumed shall be in accordance with sections 13.12.030
13.12.040, 13.12.041, 13.12.042, 13.12.043, 13.12.060, through 13.12.073, and the demand
response credits in accordance with Sections 13.12.031.D, 13.12.0401.E, and 13.12.0421.D.
The monthly rate includes all applicable taxes.
13.12.031 — Schedule R -03- Residential service time of use rate.
A. Applicability.
This schedule applies throughout the City for domestic uses in single family residences,
individual apartments or farms. Separately metered services incidental to single family
residential and farm service may be served under this schedule.
B. Character of Service.
Sixty cycle, alternating current, 120/240 volts nominal, single phase service will be furnished
under this schedule, supplied through a single meter and one point of delivery.
C. Time of Use Rate:
1. Base charge $15,75 per month.
2. Monthly energy charge between September 1 and May 31 $0.06700 per kWh during
heavy load hours, $0.05800 per kWh during medium load hours, and $0.05000 per kWh during
light load hours.
3. Monthly energy charge between June 1 and August 31 $0.06930 per kWh during heavy
load hours, $0.0599 per kWh during medium load hours, and $0.04520 per kWh during light
load hours.
-2-
•
•
4. Heavy load hours are all hours from 6:00:00 a.m. to 1:59:59 p.m. Monday through
Saturday. Medium load hours are all hours from 2:00:00 p.m. to 9:59:59 p.m. Monday
through Saturday. Light load hours are all other hours Monday through Saturday, all day
Sunday, and all day on North American Electric Reliability Corporation specified holidays.
Pacific Prevailing Time applies (Pacific Standard Time or Pacific Daylight Time, as
applicable).
D. Demand Response Credits.
Devices controlled by the City during demand events, providing the customer has not disabled
the controls or opted out of participation, shall receive a credit as follows:
1. Water heater load control switch $10.00 credit per month.
2. Smart thermostat or home area network $10.00 credit per month.
3. Water heater load control switch and smart thermostat $10.00 credit per month.
4. Thermal storage system $10.00 credit per month.
13.12.0401. Schedule GS -03 - General service time of use rate.
A. A s .licabilit . This schedule a lies to all accounts not covered b other rate schedules with
the following types of service:
1. 120/208 or 120/240 volts sin le or three .hase service . anel of 400 am s or smaller.
2.240/480 or 277/480 volts three .hase service .anel of 200 am.s or smaller.
3. Munici al traffic si nal and street li ' hts.
4. Municipal emergency management systems.
5. Cable television s stem and other communications s stems sin le .hase sower su..lies in
accordance with Section 10.2 of Ordinance no. 3116.
B. Character of Service. Sixt c cle alternating current at such .hase and voltage as
the City ma
have available will be furnished under this schedule as .lied through a single
meter and one point of delivery.
C. Time of Use Rate:
1. Base Charge
a. Single phase $21.50 per month
b. Three phase $53.75 per month
c. Municipal traffic signal $179.00 per month
d. Municipal street light $128.90 per month
e. Municipal emergency management system $27 20 per month
2. Monthly Energy Charge between se 1 and Mav 31 0.06800 kWh during heelv ly oad
hours 0.05800 . er kWh durin medium load hours and '. 0.05000 . er kWh durin ' li ' ht load
-3-
•
•
hours.
3. Monthly Energy Charge between June 1 and August 31 $0 07040 per kWh during heavy load
hours ', 0.0599 . er kWh durin medium load hours and ', 0.04520 . er kWh durin ' li ht load
hours.
4. Heav load hours are all hours from 6:00.00 A.M. to 1:59:59 P.M. Monda throu ' h
Saturday. Medium load hours are all hours from 2:00:00 P.M. to 9:59:59 P.M., Monday
through Saturday. Light load hours are all other hours Monday through Saturday, all day
Sunday, and all day on North American Electric Reliability Corporation specified holida s.
Pacific Prev. ilin ' Time a..lies Pacific Standard Time or Pacific Da li ht Time as
applicable).
5. The base charges for municipal traffic signals and street lights includes maintenance of
existing luminaries and controls by the Public Works and Utilities Department.
6. The municipal emer enc management s stem base charge shall a..1 to s stems with a
normal operating load of 150 watts or less, which shall not be required to be metered.
D. Munici p al Streets Li hts. The electric utilit rates for munici s al street li htin' shall recover
the cost of providing service. In different areas of the City, the Department shall meter
re.resentative 150 and 200 watt street lights. Each light so metered shall be char'ed a base
charge. The monthly energy charge shall be determined by multiplyin • the number of street
li ht fixtures times the monthl consum.tion determined b the metered li ' hts.
E. Demand Response Credits. Devices controlled b the City durin demand events
.rovidin' the customer has no disabled the controls or o.ted out of .artici.ation hall receive
a credit as follows:
1. Water heater load control switch $10.00 credit per month.
2. Smart thermostat or home area network $10.00 credit per month.
3. Water heater load control switch and smart thermostat $10.00 credit per month.
4. Thermal storage system $10.00 credit per month.
13.12.0411. Schedule GD -03 - General service demand time of use rate.
A. A..licabilit . This schedule ap.lies to all not covered b other rate schedules with the
following types of service:
1. 120/208 or 120/240 volts. sinele or three phase. service panel lar ' er than 400 amps.
2.240/480 or 277/480 volts three .hase service . anel lar • er than 200 am. s.
B. Character of Service. Sixty cycle, alternating current at such .hase and volta'e as the Cit
ma have available will be furnished under this schedule as.lied throu h a sin e meter and
one point of delivery.
C. Time of Use Rate:
-4-
•
•
1. Base Charge:
a. Single phase $42.95 per month
b. Three phase $107.40 per month
2. Monthly Enerev Charge between September 1 and May 31 $0.04660 per kWh during heavy
load hours 0.04660 . er kWh durin medium load hours and ', 0.03750 . er kWh durin • li • ht
load hours.
3. Monthly Energy Charge between June 1 and August 31 $0 04820�er kWh during heavy
load hours 0.04820 . er kWh durin medium load hours and 0.03390 . er kWh durin • li • ht
load hours.
4. Heav load hours are all hours from 6:00:00 A.M. to 1:59:59 P.M. Monda throu • h
Saturday. Medium load hours are all hours from 2:00:00 P.M. to 9:59:59 P.M. Monday
through Saturday. Light load hours are all other hours Monday through Saturday, all day
Sunday, and all day on North American Electric Reliability Corporation specified holidays.
Pacific Prevailin • Time a..lies Pacific Standard Time or Pacific Da li ht Time as
applicable).
5. Billing Demand:
a. Billin demand for each month shall be based on the maximum hour of KVA a..arent
power) during Heavy Load Hours.
b. Monthly Demand Charge between September 1 and May 31 $3.50 per KVA for 95% of all
KVA and $9.80 per KVA for 5% of all KVA.
c. Monthl Demand Char ' e between June 1 and Au ust 31 ', 3.50 . er KVA for 95% of all KVA
and $9.06 per KVA for 5% of all KVA.
13.12.0421. Schedule NP -03 - Nonprofit tax - deductible — time of use rate.
A. A..licabilit . This schedule a..lies to all non.rofit tax - deductible or • anizations.
B. Character of Service. Sixt c cle alternating current at such .hase and voltage as the Cit
ma have available will be furnished under this schedule ap flied throu • h a single meter and
one point of delivery.
C. Time of Use Rate:
1. Base Charge
a. Single phase $21.50 per month
b. Three phase $53.75 per month
2. Month' Ener Char e between Se tember 1 and May 31 $0.07110 per kWh durinpr heavy
load hours, $0.05770 . er kWh durin • medium load hours. and $0.04970 . er kWh durin • li • ht
load hours.
3. Monthl Energ Char e between June 1 and August 31 0.07360 kWh durinp heavy load
hours $0.05960 Der kWh durin • medium load hours. and 0.04490 er kWh durin li ht load
-5-
•
•
hours.
4. Heavy load hours are all hours from 6:00:00 A.M. to 1:59 :59 P.M., Monday through
Saturday. Medium load hours are all hours from 2:00:00 P.M. to 9:59:59 P.M., Monday
through Saturday. Light load hours are all other hours Monday through Saturday, all day
Sunday, and all day on North American Electric Reliability Corporation specified holidays.
Pacific Prevailing Time applies (Pacific Standard Time or Pacific Daylight Time, as
applicable).
D. Demand Res.onse Credits. Devices controlled b the Cit durin demand events
providing the customer has not disabled the controls or opted out of participation, shall receive
a credit as follows:
1. Water heater load control switch $10.00 credit per month.
2. Smart thermostat or home area network $10.00 credit per month.
3. Water heater load control switch and smart thermostat $10.00 credit per month.
4. Thermal storage system $10.00 credit per month.
13.12.044 Schedule GD -04 - General service demand — primary metered — time of use rate
A. Applicability. This schedule applies to all accounts not covered by other rate schedules with
the following types of service:
1. 120/208 or 120/240 volts, single or three phase, service panel larger than 400 amps.
2.240/480 or 277/480 volts, three phase service panel larger than 200 amps.
3. When electric current is measured at primary voltage and delivery to the customer is at
secondary voltage.
B. Character of Service. Sixt c cle alternatin current a such .hale and volta• e as the Cit
ma have available will be furnished under this schedule a..lied throu ' h a sin le meter and
one point of delivery.
C. Time of Use Rate:
1. Base Charge:
a. Single phase $42.95 per month
b. Three phase $107.40 per month
2. Monthly Energy Charge between September 1 and Ma 31 0.04590 Der kWh durinv heavy
load hours ', 0.04590 . er kWh durin medium load hours and 0.03690 . er kWh durin • li ht
load hours.
3. Monthly Energy Charge between June 1 and Au ust 31 0.04740 er kWh during heavy load
hours ', 0.04740 . er kWh durin medium load hours and ', 0.03330 . er kWh durin li ' ht load
hours.
4. Heav load hours are all hours from 6:00:00 A.M. to 1:59:59 P.M. Monda throu • h
Saturda . Medium load hours are all hours from 2:00:00 P.M. to 9:59:59 P.M. Monda
throu h Saturda . Li ' ht load hours are all other hours Monda throu ! h Saturda all da
-6-
•
•
Sunday, and all day on North American Electric Reliability Corporation specified holidays.
Pacific Prevailing Time applies (Pacific Standard Time or Pacific Daylight Time, as
applicable).
5. Billing Demand:
a. Billing demand for each month shall be based on the maximum hour of KVA (apparent
power) during Heavy Load Hours.
b. Monthly Demand Charge between September 1 and May 31 $3.45 per KVA for 95% of all
KVA and $9.80 per KVA for 5% of all KVA.
c. Monthly Demand Charge between June 1 and August 31 $3.45 per KVA for 95% of all KVA
and $9.06 per KVA for 5% of all KVA.
13.12.061 Schedule PS -03 - Primary service — time of use rate.
A. Ap.licability. This schedule applies to all accounts which own and operate a primary volta ' e
distribution system with a connected load greater than 1,000 KVA.
B. Character of Service. Service to be furnished under this schedule is unregulated three phase,
sixty cycle, alternating current at primary voltage, 12.5 KV nominal. Service under this
schedule shall be provided and metered at the point(s) of interconnection of the distribution
facilities of the customer and the City.
C. Time of Use Rate:
1. Base Charge: $286.35 per month
2. Monthly Energy Charge between September 1 and May 31 $0 04100 per kWh durin heavy
load hours 0.04100 er kWh durin medium load hours and 0.03300 per kWh during light
load hours.
3. Monthly Energy Charge between June 1 and August 31 $0 04240 per kWh during heavy load
hours, $0.04240 per kWh during medium load hours, and $0.02980 er kWh during li ht load
hours.
4. Heav load hours are all hours from 6:00:00 A.M. to 1:59:59 P.M. Monda throu ' h
Saturday Medium load hours are all hours from 2:00:00 P.M. to 9:59 :59 P.M. Monday
throu • h Saturday Light load hours are all other hours Monda throu • h Saturda all da
Sunda and all da on North American Electric Reliabilit Co .oration specifed h.lida s.
Pacific Prevailin Time a..lies
applicable).
5. Billing Demand:
a. Billin' demand for each month shall be based on the maximum hour of KVA apparent
power) during Heavy Load Hours.
b. Monthly Demand Charge between September 1 and Ma 31 $4.30 per KVA for 95% of all
KVA and $9.80 per KVA for 5% of all KVA.
Pacific Standard Time or Pacific Da
i
ht
Ti
e
as
-7-
•
•
c. Monthly Demand Charge between June 1 and August 31 $4.30 per KVA for 95% of all KVA
and $9.06 per KVA for 5% of all KVA.
13.12.075 Schedule MW -03 - Municipal water pumping — time of use rate.
A. Applicability. This schedule applies to municipal water pumping facilities where the
connected load is greater than 500 KVA.
B. Restrictions. Timers approved by the Public Works and Utilities Department shall be
installed to prevent pumping during restricted hours as determined by the Public Works and
Utilities Department.
C. Character of Service. Service to be furnished under this schedule is three phase, sixty cycle,
alternating current at such phase and voltage as the City may have available will be furnished
under this schedule, applied through a single meter and one point of delivery.
D. Time of Use Rate:
1. Basic Charge: $286.35 per month
2. Monthly Energy Charge between September 1 and May 31 $0 06440 per kWh durin heavy
load hours $0.06440 per kWh during medium load hours, and $0.03210 .er kWh durin light
load hours.
3. Monthly Energy Charge between June 1 and August 31 $0 06650 per kWh durin heav Iy oad
hours $0.06650 pet. kWh durin a medium load hours. and $0.02900 ner kWh durin light load
hours.
4. Heav load hours are all hours from 6:00:00 A.M. o 1:59:59 P.M. Monda throu h
Saturda Medium load hours are all hours from 2:00:00 P.M. to 9:59:59 P.M. Monda
throu h Saturda
Li ! ht load hours are all other hours Monda
through Saturda all day
Sunda_ and all da on North American Electric Reliabilit Co .oration s.ecified holida s.
Pacific Prevailin • Time applies (Pacific Standard Time or Pacific Da li • ht Time as
applicable).
5. Billing Demand:
a. Billing demand for each month shall be based on the maximum hour of KVA a..arent
power) during Heavy Load Hours.
b. Monthl Demand C are e between September 1 and Ma 31 '.3..5 .er KVA for 9 % of all
KVA and $9.80 per kW for 5% of all KVA.
c. Monthl Demand Char ' e between June 1 and Au ust 31 ', 3.65 per KVA for 95% of all KVA
and $9.06 per KVA for 5% of all KVA.
-8-
•
•
Section 2 - Corrections. The City Clerk and the codifiers of this ordinance are
authorized to make necessary corrections to this ordinance including, but not limited to, the
correction of the scrivener's /clerical errors, references, ordinance numbering,
section /subsection numbers and any references thereto.
Section 3 - Severability. If any provisions of this Ordinance, or its application to
any person or circumstances, are held invalid, the remainder of the Ordinance, or application of
the provisions of the Ordinance to other persons or circumstances, is not affected.
Section 4 - Effective Date. This Ordinance, being an exercise of a power
specifically delegated to the City legislative body, is not subject to referendum. This
ordinance shall take effect five (5) days after passage and publication of an approved summary
thereof consisting of the title.
PASSED by the City Council of the City of Port Angeles at a regular meeting of said
Council held on the 17th day of April, 2012.
ATTEST:
sa Hurd, City Clerk
PUBLISHED: April 22 2012
By Summary
MAYOR, CHERIE , IDD
APPRO1 ED AS TO FORry 7
illiam E. Bloor, City Attor
G \LEGAL\a ORDINANCES &RESOLUTIONS \ORDINANCES 2012 \05 - Electric- TlmeofUse Chapter 3 12 02 22 I2docx docx
-9-
•
Summaries of Ordinances Adopted by the
Port Angeles City Council
On April 17, 2012
Ordinance No. 3451
This Ordinance of the City of Port Angeles, Washington, revises Chapter 3.70 of the Port
Angeles Municipal Code relating to Medic I Charges.
Ordinance No. 3452
This Ordinance of the City of Port Angeles, Washington, relating to electricity services and
charges makes changes to Chapter 13.12 of Title 13 of the Port Angeles Municipal Code.
The full texts of the Ordinances are available at City Hall in the City Clerk's office, on the City's
website at www.cityofpa.us, or will be mailed upon request. Office hours are Monday through
Thursday, 8:30 a.m. to 4:00 p.m., and Friday 8:30 a.m. to 12:30 p.m. These Ordinances shall
take effect five days following the date of publication by summary.
Publish: April 22, 2012
•
Janessa Hurd
City Clerk