HomeMy WebLinkAbout31-84RESOLUTION NO.
WHEREAS, the City Council of the City of Port Angeles,
by Section 7 of Ordinance 2232, required the establishment of
fees for required electrical inspections by resolution; NOW,
THEREFORE,
BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ANGELES as follows:
Section 1. The fees for required electrical inspec-
tions shall be as stated in this Resolution; provided that said
fees shall not exceed those established in RCW 19.28.210.
(A) New Service Fees:
1 100 26.00
101 200 30.00
201 300 40.00
301 400 52.00
401 500 72.00
501 600 80.00
601 800 95.00
801 1200 100.00
1201 1600 108.00
1601 2000 166.00
2001 2500 120.00
2501 3000 128.00
3001 4000 132.00
4001 500 140.00
5001 6000 148.00
Over 6000 160.00
The fees for a temporary service for lighting and power
shall be 50% of the new service fees, except thta there
shall be a minimum fee of $16.
(B) In addition to the inspection fees as determined in Sub
Section (A) of this Section, the fee for feeder installation
shall be twenty -five percent of the fee for service installa-
tions of like ampacity with a minimum fee of $10 for each
A RESOLUTION of the City of Port Angeles
establishing new fees for electrical
inspections and rescinding Resolution
No. 22 -84
Single Phase Other Than Single Phase
Less than Over 601
600 Volts Volts
Amps 3 Phase 3 Phase
-1-
40.00 72.00
60.00 112.00
80.00 156.00
108.00 200.00
132.00 240.00
152.00 288.00
176.00 332.00
192.00 352.00
208.00 376.00
212.00 400.00
228.00 416.00
236.00 440.00
257.00 472.00
268.00 496.00
288.00 512.00
340.00 560.00
feeder when inspected at the same time as for the electrical
permit.
(C) The fee for new circuits, circuit extensions, and circuit
alterations, where the service or feeder is not modified,
shall be $16 for one to four circuits inspected at the same
time on the same premises under a single permit and $4 for
each additional circuit. The total fee shall be no greater
than the fee tor a new service of like ampacity in Sub
Section (A)
(D) To calculate the fees, the following shall be classified as
separate services:
1. Feeders that terminate in a separate building.
2. Secondaries of transformers that (a) power burglar
alarms; (b) power fire alarms; or (c) have a capacity
greater than 600 VA.
(E) The fees for fire and burglar alarms and all other low
voltage systems shall be calculated according to the number
of zones used for the premises. Zones 1 through 10 shall be
$16 when inspected at the same time and on the same premises
under a single permit and $1 for each additional zone.
(F) In addition to the inspection fee of Sub Section (A) of this
Section, a fee of $10 shall be charged for inspection of the
following additional units when inspection is at the same
location and at the same time as for the electrical permit:
1, Mobile home service in a mobile home park.
2. Mobile home feeder where service is existing in a
mobile home park.
3. Each lot in a recreational vehicle park to which power
is supplied.
4. Yard pole meter loops or similar isolated metering
installations.
5. Each unit of transient worker housing.
-2--
Outbuildings on residential property for residential
purposes served by a circuit(s) such as garages, green
houses, workshops, etc.
7. Motor 10 HP or larger.
(G) The fee for sign and outside lighting circuits is $26 for
one to four circuits inspected at the same time on the same
premises under a single permit and $1 for each additional
circuit.
(H) In addition to the service and feeder installation fees, the
fee for inspecting each electrically driver irrigation
machine is $32 plus $5 for each tower or drive motor.
(I) 1. The fee for electrical plan review when required by
Electrical Inspector per Article 215 -5 of the N.E.C.
shall be at the rate of $32 per 'hour with a minimum
charge of $32.
2. The fee for altering of an existing service or feeder
shall be 50% of a new service of the same ampacity,
provided that the fee for increasing or relocating of
any service shall be the same as new services.
(J) An additional fee of $32 minimum and $16 for each one -half
hour shall be paid before approval of the installation if
the following services are necessary:
1. Trips to inspect when the permit applicant has given
notice to the inspector that the work is ready for
inspection when it is not, or if the applicant has
given erroneous address.
2. More than one additional inspection permit to inspect
corrections required by the inspector as a result of
carelessness or neglect, or for improperly responding
to a corrective notice.
3. Trips required to remove a red tag from the job site
posted because uncertified electricians were working on
the job site.
-3-
4. Trips required when corrections have not bee n made in
the prescribed time, unless an exception has been
requested and granted.
(K) The fee for emergency, standby, and resource recovery
generators up to 50 KW is $32. The fee for a generator
installation larger than 50 KW that constitutes the main
power source shall be the same as for the applicable
services and feeders in Sub Sections (A) and (B) of this
Section.
(L) A person or business that fails to submit a fee and to ob-
tain an electrical wiring permit for a completed electrical
job before the Department inspect the work shall pay double
the fee of a new permit.
(M) On jobs requiring partial or progress inspections, "one" in-
spection is allowed per $32 fee in Sub Section (A). Addi-
tional inspections will be at the fee in Sub Section (J)
this Section.
(N) Fees for carnival electrical inspections:
1. At the option of a carnival operator, the Department
will, for $32 an hour, inspect carnival rides, con-
cessions, and generators before the first local opening
each year.
2. If a ride, concession, or generator has not had a pre-
opening inspection, a carnival, circus, or traveling
-4--
show must pay a fee of $16 for each ride, concession or
generator which uses or supplies power. An insignia of
inspection will be affixed to each ride, concession,
and generator to indicate the inspection date and
whether the inspection was passed or failed.
3. Each additional time the ride, concession or generator
is set up, for those rides, concessions, and generators
that have been inspected and have insignia of inspec-
tion, the fee shall be $64 for up to the first ten
insignia of inspection, the fee for that ride,
concession or generator shall be that charged in (2) of
this Sub Section.
(0) Inspection(s) requested by the customer for any existing
electrical facilities shall be $32 for single phase, $64 for
three phase of less than 800 amps, or $80 for three phase
equal to or greater than 800 amps.
Section 2. Resolution 22 -84 is hereby rescinded.
Section 3. This Resolution shall take effect
immediately.
PASSED by the City Council of the City of Port Angeles
at a regular meeting of said Council held on the O day of
k 1984.
ATTEST:
rides, concessions or generators, and $1 for subsequent
rides. If a ride, concession or generator has no
7 /-1/
Merri/A. Lannoye, City Clerk
APPRO ED, AS TO FO1i:
Craig D. [Hutson, City Attorney
PUBLISHED 4.<_- `C_ j.-Gr k7 I2A9<