HomeMy WebLinkAbout000092 Amendment (3)THIS AMENDMENT NO. 3 is made and entered into this V t day of November, 2012, by and
between the City of Port Angeles, a non charter code city of the State of Washington, (hereinafter
called the "CITY and Studio, Cascade Inc., a Washington Corporation (hereinafter called the
"CONSULTANT
AMENDMENT NO. 3 TO THE
AGREEMENT FOR PROFESSIONAL SERVICES
BETWEEN
THE CITY OF PORT ANGELES
AND
STUDIO CASCADE, INC
PROJECT WTIP
NOW, THEREFORE, in consideration of the representations and the terms, conditions, covenants
and agreements set forth in the original AGREEMENT and this AMENDMENT, the parties hereto
agree as follows:
SECTION 1
The CITY entered into an AGREEMENT with the CONSULTANT on May 5, 2011 (the
AGREEMENT).
SECTION 2
I. TIME OF PERFORMANCE
Section IV of the original Agreement is amended to read as follows:
The CONSULTANT may begin work upon execution of this Agreement by both parties and
the duration of the Agreement shall extend through October 31, 2013. The work shall be
completed in accordance with the schedule set forth in attached Exhibit C. All work of item
6 shall be completed by October 31, 2013.
II. MAXIMUM COMPENSATION
Section VI of the Agreement is amended as follows:
The not to exceed amount is increased from $1,299,622 to $1,346,527, an additional amount
of $46,905.
III. REVISED EXHIBITS
EXHIBIT "A" is amended adding the following additional work to item 6 (Construction
Support), as follows:
000092
CITY OF PORT ANGELES
B
ATTEST:
City Manager
Zenovic
Inspection coordination between construction manager and designers of record as
required; provide sampling, testing, and follow -up report for the removal of existing
Underground Storage Tanks within the Esplanade excavation area
KPFF
Review of specialized structural submittals, respond to Requests for Information,
review shop drawings, and provide as -built plans based on contractor and
construction manager provided mark -ups
Hart Crowser
Review of pile driving plan and associated submittals, full time on site inspection
during three weeks of pile driving, including development of pile driving criteria,
daily pile capacity review and approval, pre construction meeting, and preparation of
final completion letter
Studio Cascade
General project coordination between City and technical subcontractors as requested
for the work of this amendment.
EXHIBIT "C" is amended adding $46,905.00 to existing Task 6 for a new Task 6
budget amount of $86,905.00.
SECTION 3 RATIFICATION
As modified herein, the AGREEMENT is confirmed and ratified.
In WITNESS WHEREOF, the parties hereto have executed this Amendment No. 3 to the Agreement
as of the date and year first written above.
Jams a Hurd, City lerk
APPROVED AS TO FORM:
William E. Bloor, City Attorney
STUDIO CASCADE, INC