HomeMy WebLinkAbout000104 AmendmentSERVICE ORDER 1 TO THE
CONTRACT FOR SANITARY SEWER SYSTEM CLEANING VIDEOING
QETWEEN THE
THE CITY OF PORT ANGELES
AND
PACIFIC CONCRETE SERVICES
WW -11 -036
RELATING TO: CONTRACT FOR SANITARY SEWER SYSTEM CLEANING
VIDEOING, WW -11 -036
This Service Order No. 1 is made and entered into this l 7 Tit day of ffB 2012,
by and between THE CITY OF PORT ANGELES, a non charter code city of the State of
Washington, (hereinafter called the "CITY and Pacific Concrete Services, a
Washington Corporation (hereinafter called the "CONSULTANT
The Service Order is being entered pursuant to the Contract titled "Sanitary Sewer
System Cleaning Videoing" WW -11 -036, which was entered into on January 24, 2012.
Service Order No.1 contains the first work phase requirements.
I SCOPE OF SERVICES
The scope of professional services to be performed and the results to be achieved by the
CONNTRACTOR for the task identified in the attached Exhibit Al. The CONTRACTOR
shall provide and furnish all services and material necessary to accomplish the Task
identified in Exhibit Al.
II TIME OF PERFORMANCE
Service Order No. 1 shall be completed by March 16, 2012.
III MAXIMUM COMPENSATION
The maximum compensation, including tax, is $15,000 for this Service Order.
IV EXHIBITS
This Task Order, including its exhibits, constitutes the entire Task Order, supersedes all prior written or oral
understandings, and may only be changed by a written agreement by both parties. The following exhibits are
hereby made a part of this Task Order:
Exhibit Al Scope of Services No. 1
Exhibit 81 Maps of Inspection Locations (12 Sheets)
Exhibit C1 Price Sheet
WW -11 -036
Task Order 1, Page 1 2/8/2012
V SIGNING
In WITNESS THEREOF, the parties hereto have executed this Service Order to the Contract
as of the day and year first written above.
CITY OF PORT ANGELES:
CITY MANAG
CONTRACTOR:
Div i9�L iii0/t//f
TITLE:
APPROVED AS TO FORM:
CITY ATTORNEY
ATTEST:
WW- 11-036
Task Order 1, Page 2 2/8/2012
EXHIBIT Al Scope of Services Tasks
Contractor shall provide the following services related to Contract for Sanitary Sewer System cleaning
Videoing, WW -11 -036:
1. The Contractor shall perform video inspection of the sanitary sewer system in the order provided in
Exhibit C1.
2. Video inspection will be performed without prior cleaning of the sanitary sewer system unless it is
determined by the contractor that the sewer system condition requires prior cleaning.
3. Sewer system line lengths shown on Exhibit C1 are approximate. Line lengths will be adjusted to
reflect measured distances from manhole center to manhole center, or manhole center to cleanout,
whichever is appropriate as determined by Contractor or the Project Manager.
4. Sewer system line materials shown on Exhibit C1 shall be corrected if differing material is shown
on the videos by the Contractor or by the Project Manager.
5. The Project Manager may change the order of work or location of work for the benefit of the City.
6. The maximum compensation, including tax, for Task 1 is $15,000. A working copy of the Exhibit
C1 spreadsheet will be updated daily by the Project Manager. Inspection shall cease when the
cost of work (cleaning and inspection) reaches the $15,000 limit.
This Service Order does not alter the provisions of the Original Contract dated January 24, 2012.
Exhibit B1 Maps of Inspection Locations
(12 Sheets)
CSII
egl
V°
CO
I'.I 4.RO.Z1..19iO4,09' .101 7::. 7,
I f) -r- )s'eseto
0 -<1 c.??
lt
c_-) ..c- 1
4
Ty,
1
.c.
111 ti
1
..0
1 t,
CO 0) 1
U P (I)
co SCC!'
N
1
1.41'1 i
0,4 "''1111 jahlr. r "R
1 —1
0 4 N•fri.
u ,=„Ti
to
c,
c3) ,,t__ S .r 'r!
ci
K2
I
1 ,1
1 Fr V ILO.
I')
0
i,,
CM
'Cr :J
3
,t
JJ
6
5
s
,Y,14:17C101:1179, .11V871706)79
i .1 0 I
r i
N
Cn
—0
!I CU
r
1
i
o
AMMO.
asolli
m•P
Exhibit C1 Price Sheet
SANITARY SEWER SYSTEM CLEANING AND VIDEOING,
TASK ORDER 1
EXHIBIT Cl PRICE SHEET
No Street /Alley
1 Georgiana /Front Alley
2 Caroline /Georgiana Alley
2 Caroline Georgiana Alley
3 Caroline Georgiana Alley
4 Georgiana /Front Alley
5 Georgiana /Front Alley
6 Front /First Alley
7 First /Second Alley
8 Second/Third Alley
9 Third /Fourth Alley
10 Fourth /Fifty Alley
11 Fifth /Sixth Alley
12 Sixth /Seventh Alley
13 Seventh /Eighth Alley
14 Eights /Ninth Alley
15 Ninth/Tenth Alley
15 Ninth/Tenth Alley
16 Francis St
16 Francis St
17 Francis 5t
18 Francis St
19 First /Second Alley
20 Second St
21 Second/Third Alley
22 Third /Fourth Alley
23 Second/Third Alley
24 Third /Fourth Alley
25 Fourth /Fifty Alley
26 Fifth St
27 Dolan Ave
28 Hancock Ave
29 Orcas St
30 Orcas St
31 Thirteenth /Fourteenth Alley
32 Fourteenth /Fifteenth Alley
33 Fifteenth /Sixteenth Alley
34 Pine St
35 Sixteenth Street
36 Fifth /Sixth Alley
37 Sixth /Seventh Alley
38 Railroad Ave
38 Railroad Ave
39 Oak St
39 Oak St
40 Eighth /Ninth Alley
41 Eighth /Ninth Alley
42 Eighth /Ninth Alley
From
Race St
Francis St
50' East of Francis St
Race St
Washington St
Chambers 5t
Chambers St
Jones St
Jones St
Jones St
Jones St
Washington St
Washington St
Race St
Race St
Race St
80' West of Washington St
Second/Third Alley
First /Second Alley
First /Second Alley
Front /First Alley
Ennis St
Ennis St
Ennis St
Ennis St
Wolcott St
Wolcott St
Wolcott St
Wolcott St
Oak St
Oak St
laurel St
100' West of Lincoln St
Cedar St
Cedar 5t
Cedar St
Fourteenth /Fifteenth Alley
Cedar St
D St
D St
Oak St
Mid -block
Front St
40' N of Front St
Laurel St
Lincoln St
Chase St
To
Washington St
50' East of Francis St
Race St
Washington St
Chambers St
Jones St
Jones St
Liberty St.
Liberty St
Liberty St
Liberty St
Chambers St
Chambers St
Washington St
Washington St
80' West of Washington St
Washington St
First /Second Alley
First /Second Alley
Front /First Alley
Georgiana /Front Alley
Alder St
Alder St
Alder St
Alder St
Penn St
Penn St
Penn St
Penn St
Laurel St
Laurel St
100' West of Lincoln St
270' West of Orcas St
Pine St
Pine St
Pine St
Fifteenth /Sixteenth Alley
Pine St
C St
C St
Mid -block
Laurel St
40' N of Front St
Railroad Ave
Lincoln St
Chase St
Peabody St
NOTE 1 Pipe lengths are approximate Payment will be based on measured distance from maanhole centerlines
2 Contractor to verify pipeline materials
3 Cleaning Cost and CCTV Cost includes Tax of 8 4%
From Through Pipe
Manhole Line To Manhole Material Pipe Length Cleaning CCTO Price Cleaning Cost
Asset ID Asset ID Asset ID Pipe Dia (in) (2) (ft) (1) Price /If) /If) (3) CCTV Cost (3)
1030 1475 987 15 Conc 580 0 60 0 55 377 23 345 80
1139 452 1090 12 Conc 52 0 60 0 55 33 82 31 00
1090 1473 1091 12 Conc 425 0 60 0 55 276 42 253 39
1091 2312 1031 10 Conc 530 0 60 0 55 344 71 315 99
987 1303 2131 8 Conc 475 0 60 0 55 308 94 283 20
2131 1585 2102 8 Conc 530 0 60 0 55 344 71 315 99
2101 662 2062 6 Conc 490 0 60 0 55 318 70 292 14
1998 2297 1999 6 Conc 520 0 60 0 55 338 21 310 02
1997 2615 1961 6 Conc 520 0 60 0 55 338 21 310 02
1960 297 2170 6 Conc 520 0 60 0 55 338 21 310 02
2169 697 915 6 Conc 520 0 60 0 55 338 21 310 02
2165 414 2166 6 Conc 540 0 60 0 55 351 22 321 95
2164 2774 910 6 Conc 540 0 60 0 55 351 22 321 95
907 182 909 6 Conc 455 0 60 0 55 295 93 271 27
903 1201 1621 6 Conc 470 0 60 0 55 305 69 280 21
1619 224 842 6 Conc 440 0 60 0 55 286 18 262 33
842 618 843 6 Conc 81 0 60 0 55 52 68 48 29
2126 2766 983 24 Conc 350 0 60 0 55 227 64 208 67
983 885 984 30 0 60 0 55 19 51 17 89
984 2772 1027 24 Conc 350 0 60 0 55 227 64 208 67
1027 1634 1864 30 Conc 370 0 60 0 55 240 65 220 59
1962 2621 2174 6 Conc 440 0 60 0 55 286 18 262 33
2172 1581 918 6 Conc 440 0 60 0 55 286 18 262 33
2171 1582 917 6 Conc 565 0 60 0 55 367 48 336 85
916 1573 252 6 Conc 400 0 60 0 55 260 16 238 48
1636 2653 856 8 Conc 400 0 60 0 55 260 16 238 48
853 2654 855 8 Conc 400 0 60 0 55 260 16 238 48
1931 724 1934 8 Conc 400 0 60 0 55 260 16 238 48
1932 166 624 8 Conc 450 0 60 0 55 292 68 268 29
1654 1165 1655 8 Conc 540 0 60 0 55 351 22 321 95
865 1382 867 8 540 0 60 0 55 351 22 321 95
870 1151 873 6 350 0 60 0 55 227 64 208 67
873 2281 875 6 7 400 0 60 0 55 260 16 238 48
898 2326 2021 6 Conc 520 0 60 0 55 338 21 310 02
1551 1550 2022 6 Conc 520 0 60 0 55 338 21 310 02
2039 1543 2040 6 Conc 520 0 60 0 55 338 21 310 02
2022 2328 2040 8 Conc 380 0 60 0 55 247 15 226 56
276 2078 1976 6 Conc 440 0 60 0 55 286 18 262 33
1074 1401 1663 6 Conc 490 0 60 0 55 318 70 292 14
1661 667 1662 6 Conc 480 0 60 0 55 312 19 286 18
1434 1227 1504 18 Conc 295 0 60 0 55 191 87 175 88
1504 1002 1505 18 Conc 310 0 60 0 55 201 62 184 82
1501 3215 12976 18 Conc 40 0 60 0 55 26 02 23 85
12976 262 1434 18 Conc 330 0 60 0 55 214 63 196 75
2166 1741 2030 24 Conc 525 0 60 0 55 341 46 313 01
2030 993 2084 24 530 0 60 0 55 344 71 315 99
2084 900 2049 12 Conc 475 0 60 0 55 308 94 283 20
19388