U [n
ORDER FOR MINOR CHANGES No.1
Date:1/15/2015
Owner: City of Port Angeles
Contract Title: 4th Street Stormwater Improvements, DR03-2009
Contractor: Jordan Excavating
Subject: Rain Garden Scupper Settling Block
Project Manager: Jonathan Boehme
Bid Item No: A-1
®Ordered by Contracting Agency ❑Changed proposed by the Contractor E]Change in scope
Change Description:
Stormwater carrying sediments enter the rain gardens through scupper inlets. A
concrete block will be placed at each inlet and be surrounded by quarry spalls to
dissipate the energy of the water and allow the sediments to settle out on a flat
surface that can be easily cleaned. Blocks will be installed in up to 202 inlets at a
cost of $11.00 each.
All Work,materials and measurements to be in accordance with the provisions of the original contract and/or the standards specifications
and special provisions for the type of construction involved.The payments and/or additional time specified and agreed to in this order
include every claim by the Contractor for extra payment or extension of time with respect to the work described herein,including delays to
the overall project.
Original Bid Item Amount Current Bid Item Amount Cost this Change Est.Remaining Bid Item Amount
$40,000 $40,000 $2222.00 $37,778.00