September 28, 2000
Burst Wireless
c/o Mr. Steve Kaplan
575 Andover Parkway
Tukwila, WA 98188
RE:
Conditional Use Permit - CUP 00-07
BURST WIRELESS - 716 South Chase Street
Dear Mr. Kaplan:
As you know, following a public hearing conducted on September 27,2000, the City Planning
Commission approved a conditional use permit to allow a cellular tower to be erected in the
Community Shopping District with the following conditions:
Conditions:
1. The equipment and its operation shall be in compliance with Federal Communication
Commission licensing requirements for such facilities.
2. A City of Port Angeles building permit shall be obtained for the tower structure prior
to placement.
3. A landscaping plan shall be submitted for approval by the Planning Department prior
to issuance of a building permit for the tower. The plan shall be limited to the screening
of the base structure and tower and shall incorporate fast-growing, tall evergreens on the
subject property. The plan shall be implemented at the appropriate planting period upon
receipt of a permanent license, not to exceed one year from the date of approval of the
conditional use permit.
4. An easement shall be obtained and legally recorded for the retention of the trees located
on the Ralston property to the north. The term of the easement shall be for the period
that the tower exists on the subject property.
5. Should the applicant not obtain a permanent license, the tower and associated utility
structures shall be removed and the site restored to its original condition.
321 EAST FIFTH STREET. P. O. BOX 1150. PORT ANGELES. WA 98362-0217
PHONE: 360-417-4750 . FAX: 360-417-4609 . TTY: 360-417-4645
E-MAIL PLANNING@CI.PORT-ANGELES.WA.US
. \
'''\
".....
"". .
~
'"
".....J
"-.
\0-
~
~
..~
~
l:\.
"
Burst Wireless letter
September 28, 2000
6. Fencing shall be provided around the tower structure and any associated utility
structures in order to address safety concerns.
7. The tower structure should be moved to the northwest comer of the property to
maximize shielding of the structure. A site plan depicting the new location shall be
provided to the Planning Department for approval prior to issuance of a building permit.
The decision of the Planning Commission is final unless an appeal is received of the decision
within 14 days of the action. If you have any questions or if we can provide further assistance,
please don't hesitate to contact the Planning Department.
Sincerely,
~,'1'~~
Planning Specialist
cL/ Building Division