PREPARED 10/21/16, 9:01:53 INSPECTION TICKET PAGE 4
CITY OF PORT ANGELES INSPECTOR: JAMES LIERLY DATE 10/21/16
------------------------------------------------------------------------------------------------
ADDRESS . : 1110 DUNKER DR SUBDIV:
CONTRACTOR : ACE MICHAELS INC PHONE (360) 460-6172
OWNER ACE MICHAELS INC PHONE (360) 460-6172
PARCEL 06-30-01-8-3-0070-0000-
APPL NUMBER: 16-00000774 RES NEW SFR
----------------—--------------------------------------------—-—----------------------------
REQUESTED INSP DESCRIPTION
TYP/SQ COMPLETED RESULT RESULTS/COMMENTS
--------------- --
-
----- - ------
-------------'--------'--—---—-------------—---------——----—--
PL99 01 10/21/16 L PLUMBING FINAL
October 21, 2016 8:36:54 AM jlierly.
------------------------lw------ COMMENTS AND NOTES --------------------------------------
PREPARED 10/21/16, 9:01:53 INSPECTION TICKET PAGE 3
CITY OF PORT ANGELES INSPECTOR: JAMES LIERLY DATE 10/21/16 -
--—-—-------—-------------------------------------------------------------------------------
ADDRESS 1110 DUNKER DR SUBDIV:
CONTRACTOR ACE MICHAELS INC PHONE (360) 460-6172
OWNER ACE MICHAELS INC PHONE (360) 460-6172
PARCEL 06-30-01-8-3-0070-0000-
APPL NUMBER: 16-00000774 RES NEW SFR
------------------------------------------------------------------------------------------------
PERMIT: BPR 00 BUILDING PERMIT - RESIDENTIAL
REQUESTED INSP DESCRIPTION
TYP/SQ COMPLETED RESULT RESULTS/COMMENTS
-----------------------------------------— --- - --
BL1 01 7/05/16 PB BLDG FOUNDATION FOOTING
7/06/16 AP July 5, 2016 9:55:07 AM pbarthol.
Mike 460-6172
July 6, 2016 11:09:28 AM pbarthol.
BL2 01 7/13/16 JLL BLDG FOUNDATION STEM WALL
7/13/16 AP July 13, 2016 8:26:06 AM jlierly. -
Mike 460-6172
July 13, 2016 3:51:24 PM jlierly.
EFF O1 7/25/16 JLL BLDG FLOOR FRAMING -
7/25/16 AP July 25, 2016 9:26:07 AM jlierly.
Mike 460-6172
July 25, 2016 3:47:03 PM jlierly.
BEXS O1 8/08/16 JLL BLDG EXTERIOR SHEETING
8/08/16 AP August 8, 2016 8:52:16 AM jlierly.
Mike 460-2722
August 8, 2016 4:26:41 PM jlierly.
BL3 01 9/01/16 JLL BLDG FRAMING
9/01/16 AP September 1, 2016 8:26:23 AM jlierly.
Mike 460-774
September 1, 2016 4:47:42 PM jlierly.
BEXS 02 9/15/16 JLL BLDG EXTERIOR SHEETING
9/15/16 AP September 15, 2016 8:48:50 AM jlierly.
Mike 460-6172
September 15, 2016 3:20:10 PM jlierly.
PW99 01 10/19/16 RV PUBLIC WORKS FINAL
10/20/16 AP October 20, 2016 12:48:56 PM rvess.
Q
October 20, 2016 12:49:17 PM rvess.
BL99 01 10/21/16 BLDG FINAL
October 21, 2016 8:35:59 AM jlierly.
Mike 460-6172
------------------------------------------------------------------------------------------------
PERMIT: ME 00 MECBANICAL PERMIT
REQUESTED INSP DESCRIPTION
TYP/SQ COMPLETED RESULT RESULTS/COMMENTS
------------------------------------------------------------------------------------------------
ME99 01 10/21/16 LL MECHANICAL FINAL
- October-21, 2016 8:36:34 AM jlierly.
PERMIT: PL 00 PLUMBING PERMIT
REQUESTED INSP DESCRIPTION
TYP/SQ COMPLETED RESULT RESULTS/COMMENTS -
------------------------------------------------------------------------------------------------
PL2 01 8/16/16 JLL PLUMBING ROUGH-IN '
8/16/16 AP August 16, 2016 11:09:39 AM jlierly.
Mike
August 16, 2016 3:57:34 PM jlierly.
----------------------------------- CONTINUED ONTO NEXT PAGE -----------------------------------
%�. CITY OF PORT ANGELES
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT- BUILDING DIVISION
321 EAST 5TH STREET, PORT ANGELES, WA 98362
Application Number . . . . . 16-00000774 Date 8/16/16
Application pin number . . . 289646
Property Address . . . . . . 1110 DUNKER DR REPORT SALES TAX
ASSESSOR PARCEL NUMBER: 06-30-01-8-3-0070-0000-
Application type description RES NEW SFR on your state excise tax form
Subdivision Name . . . . . . to the City of Port Angeles
Property Use
Property Zoning . . . . . . . RS9 RESDNTL SINGLE FAMILY (Location Code 0502)
Application valuation . . . . 138650 1 11
-----------------------------------------------------------
Application desc
1882sf single story 3bed 2bath SFR
Owner Contractor 1
I ------------------------ ------------------------
L ACE MICHAELS INC ACE MICHAELS INC
1329 W 10TH ST 1329 W. 10TH ST.
PORT ANGELES WA 98363 PORT ANGELES WA 98363
(360) 460-6172 (360) 460-6172
----------------------------------------------------------------------------
Permit . . . . . . BUILDING PERMIT -RESIDENTIAL
Additional desc SFR BUILDING PERMIT
Permit Fee . . . . 1238.65 Plan Check Fee .00
Issue Date 7/01/16 Valuation . . . . 138650
Expiration Date 2/04/17
7
= Qty Unit Charge Per Extension
BASE FEE 1020.25
39.00 5.6000 THOU BL-100,001-500K (5.60 PER K) 218.40
----------------------------------------------------------------------------
Permit . . . . . . MECHANICAL PERMIT
Additional desc . . NEW SFR
Permit Fee . . . . 171.20 Plan Check Fee .00 "
Issue Date . . . . 8/16/16 Valuation . . . . 0
Expiration Date 2/12/17
Qty Unit Charge Per Extension f z. xF
BASE FEE 50.00
1.00 14.8000 EA ME-FURN/HP/FAU < OR = 5 TON 14.80
3.00 7.2500 EA ME-VENT FAN (SINGLE DUCT) 21.75
.00 10.6500 EA ME-VENT SYSTEM .00
1.00 10.6500 EA ME-HOOD/DUCT-MECH. EXHAUST 10.65
.00 18.2000 EA ME-FURN/HP/FAU > 5 TON .00
5.00 14.8000 EA ME-HEATER(SUSP/WALL/FLOOR-MTD) 74.00
----------------------------------------------------------------------------
Permit . . . . . . PLUMBING PERMIT
Additional desc . . NEW SFR
Permit Fee . . . . 170.00 Plan Check Fee .00
Issue Date 8/16/16 Valuation 0
Expiration Date 2/12/17
Qty Unit Charge Per Extension
BASE FEE 50.00
9.00 7.0000 EA PL-PLUMBING TRAP 63.00
Separate Permits are required forelectrical work,SEPA,Shoreline,ESA,utilities,private and public improvements. This permit becomes
null and void if work or construction authorized is not commenced within 180 days,if construction or work is suspended or abandoned
for a period of 180 days after the work has commenced, or if required inspections have not been requested within 186 days from the
last inspection. I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions
of laws and ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does
not presume to give authority to violate or cancel the provisions of any state or local law regulating construction or the performance of
construction.
Date Print Name Signature of Contractor or Authorized Agent Signature of Owner(if owner is builder)
T:Forms/Building Division/Building Permit
BUILDING PERMIT INSPECTION RECORD
PLEASE PROVIDE A MINIMUM 24-HOUR NOTICE FOR INSPECTIONS
Building Inspections 417-4815 Electrical Inspections 417-4735
Public Works Utilities 417-4831 Backflow Prevention Inspections 417-4886
IT IS UNLAWFUL TO COVER, INSULATE OR CONCEAL ANY WORK BEFORE INSPECTED AND ACCEPTED.
POST PERMIT INCONSPICUOUS LOCATION. KEEP PERMIT AND APPROVED PLANS AT JOB SITE.
Inspection Type Date Accepted By Comments
FOUNDATION:
Footings
Stemwall
Foundation Drainage/Downspouts
Piers
Post Holes(Pole Bldgs.)
PLUMBING:
Under Floor/Slab
Rough-in
Water Line Meter to Bldg)
Gas Line
Back Flow/Water
AIR SEAL:
Walls
Ceiling
FRAMING:
Joists/Girders/Under Floor
Shear Wall/Hold Downs
Walls/Roof/Ceiling
Drywall Interior Braced Panel Only)
T-Bar
INSULATION:
Slab
Wall/Floor/Ceiling
MECHANICAL:
Heat Pump/Furnace/FAU/Ducts
Rough-in
Gas Line
Wood Stove/Pellet/Chimney
Commercial Hood/Ducts
MANUFACTURED HOMES:
Footing/Slab
Blocking&Hold Downs
Skirting
PLANNING DEPT. Separate Permit#s SEPA:
Parking/Li hting ESA:
Landscaping SHORELINE:
FINAL INSPECTIONS REQUIRED PRIOR TO OCCUPANCY/USE
Inspection Type Date Accepted By
Electrical 417-4735
Construction - R.W. PW I Engineering 417-4831
Fire 417-4653
Planning 417-4750
Building 417-4815
i
. CITY OF PORT ANGELES
P� DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT- BUILDING DIVISION
321 EAST 5TH STREET, PORT ANGELES, WA 98362
Page 2
Application Number . . . . . 16-00000774 Date 8/16/16
Application pin number . . . 289646 REPORT SALES TAX
Qty Unit Charge Per Extension on your state excise tax form
1.00 7.0000 EA PL=WATER LINE 7.00
to the Cit of Port Angeles
4.00 7.000 EA PL DRAIN VENT
0 PIPING 28.00
Y
9
1.00 15.0000 EA PL-SEWER LINE 15.00 (Location Code 0502) ;
1.00 7.0000 EA PL-WATER HEATER 7.00
Permit . . . . . . PUBLIC WORKS RES WATER SERV
Additional desc 3/4 INCH DROP IN METER
Permit Fee . . . . 420.00 Plan Check Fee .00
j
Issue Date . . . . 7/01/16 Valuation . . . . 138650
Expiration Date 2/04/17
Qty Unit Charge Per Extension
1.00 420.0000 EA PW WATER METER DROP IN 420.00
Permit . . . . . . SANITARY SEWER HOOK UP
Additional desc . .
Permit Fee . . . . 150.00 Plan Check Fee .00
Issue Date . . . . 7/01/16 Valuation . . . . 138650
Expiration Date 2/04/17
Qty Unit Charge Per Extension
1.00 150.0000 EA SAN SEWER HOOKUP 150.00
---------------------------------------------------------------------------
Special Notes and Comments
May 27, 2016 3:38:52 PM pbarthol.
No plan check fee paid. Fee was paid on
permit 15-164, and the approved plans
will be used on this project. pb
July 7, 2016 9:30:13 AM msanders.
Residential Sprinkler system required. Spoke to Mike
Caudill via phone 7-7-2016 to confirm this requirement
May 31, 2016 7:53:30 AM rbecker.
If you are installing a lawn sprinkler system, you will need
to install a double check valve assembly.
Are you installing a fire system? If it is a closed system,
you will need to install a double check valve assembly. If
it is an open system, you do not need a backflow.Lawn or
fire system question was not marked on the application.
If you have any questions call Ron Becker at 417-4886,
fax:452-4972, or E-mail: rbecker@cityofpa.us
Electrical load calculations and electrical permits are
required.
Use existing driveway opening.
1. Establishing Construction Access.
2. Install sediment controls BMPs.
3. Stabilize exposed soils.
4. Protect slopes from erosion.
5. Protect drain. inlets.
6. Control pollutants including but not limited to spills,
Separate Permits are required for electrical work,SEPA,Shoreline,ESA,utilities,private and public improvements. This permit becomes
null and void if work or construction authorized is not commenced within 180 days,if construction or work is suspended or abandoned
for a period of 180 days after the work has commenced, or if required inspections have not been requested within 180 days from the
last inspection. I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions
of laws and ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does
not presume to give authority to violate or cancel the provisions of any state or local law regulating construction or the performance of
construction.
Date Print Name Signature of Conteactor or Authorized Agent Signature of Owner(if owner is builder).
T:Forms/Building Division/Building Permit
BUILDING PERMIT INSPECTION RECORD
PLEASE PROVIDE A MINIMUM 24-HOUR NOTICE FOR INSPECTIONS-
Building Inspections 417-4815 Electrical Inspections 417-4735
Public Works Utilities 417-4831 Backflow Prevention Inspections 417-4886
IT IS UNLAWFUL TO COVER, INSULATE OR CONCEAL ANY WORK BEFORE INSPECTED AND ACCEPTED.
POST PERMIT INCONSPICUOUS LOCATION. KEEP PERMIT AND APPROVED PLANS AT JOB SITE.
Inspection Type Date Accepted By Comments
FOUNDATION:
Footings
Stemwall
Foundation Drainage/Downspouts
Piers
Post Holes(Pole Bldgs.)
PLUMBING:
Under Floor/Slab
Rough-In
Water Line Meter to Bldg)
Gas Line
Back Flow/Water
AIR SEAL:
Walls
Ceiling
FRAMING:
Joists/Girders/Under Floor
Shear Wall/Hold Downs
Walls/Roof/Ceiling
Drywall Interior Braced Panel Only)
T-Bar
INSULATION:
Slab
Wall/Floor/Ceiling
MECHANICAL:
Heat Pump/Furnace/FAU/Ducts
Rough-In
Gas Line
Wood Stove/Pellet/Chimney
Commercial Hood/Ducts
MANUFACTURED HOMES:
Footing/Slab
Blocking&Hold Downs
Skirting
PLANNING DEPT. Separate Permit#s SEPA:
Parking/Lighting ESA:
Landscaping SHORELINE:
FINAL INSPECTIONS REQUIRED PRIOR TO OCCUPANCY/USE
Inspection Type Date Accepted By
Electrical 417-4735
Construction - R.W. PW /Engineering 417-4831
Fire 417-4653
Planning 417-4750
Building 417-4815
��►� CITY OF PORT ANGELES
DEPARTMENT� 1► TMENT OF COMMUNITY & ECONOMIC DEVELOPMENT- BUILDING DIVISION
321 EAST 5TH STREET, PORT ANGELES, WA 98362
Page 3
Application Number . . . . . 16-00000774 Date 8/16/16
Application pin number . . . 289646
- ---------------------------------------- ------------------- REPORT SALES TAX
Special Notes and Comments on your state excise tax form
concrete wash out, exposed aggregate processes, concrete to the City of Port Angeles
grindingand saw cut waste water.
7. Maintain temporary and permanent erosion control BMPS (Location Code 0502)
during project.
All disturbed area's on site not covered by new improvements
should meet the attached soil quality and depth standard.
Consider applying for the City Green Infrastructure Rebate
of up to $750.00 towards the materials to install rain
garden to control roof and driveway runoff. Also rebates
available for downspout disconnections.Contact Jonathan
Boehme at 360 417-4811
Sanitary sewer connection inspection is required by
Public Works prior to back fill of ditch. 24 hour advance
notice is required. Public Works Inspection request line
417-4831
Trench safety per applicable laws. Temp erosion control and
surface restoration responsibility of applicant. Contact
City inspector prior to start of work @ 360 417-4831. No
attachment to sanitary sewer of stormwater roof leaders,
foundation drains, yard drains, or any other CSO
contribution is allowed.
-The contractor making the connection to an existing water
meter is responsible to adjust water meter depth so that
there is a minimum of 4 to 6 inches of clearance between the
bottom of the meter box lid and the top of the meter at
finish grade.
----------------------------------------------------------------------
Other Fees . . . . . . . . . CITY DRA g 47.32
DRA FEES PLUS INTEREST 1427.73
RES UNDERGRND SERVICE FEE 770.00
SEWER SYSTEM DELV CHARGE 2260.00
STATE SURCHARGE 4.50
PW WATER SYSTEM USE FEE 2260.00
Fee summary Charged Paid Credited Due
----------------- ---------- ---------- ---------- ----------
Permit Fee Total 2149.85 2149.85 .00 .00
Plan Check Total .00 .00 .00 .00
Other Fee Total 6769.55 6769.55 .00 .00
Grand Total 8919:40 8919.40 .00 .00
Separate Permits are required forelectrical work,SEPA,Shoreline,ESA,utilities,private and public improvements. This permit becomes
null and void if work or construction authorized is not commenced within 180 days,if construction or work is suspended or abandoned
for a period of 180 days after the work has commenced, or if required inspections have not been requested within 180 days from the
last inspection. I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions
of laws and ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does
not presume to give authority to violate or cancel the provisions of any state or local law regulating construction or the performance of
construction.
Date Print Name Signature of Contractor or Authorized Agent Signature of Owner(if owner is builder)
T:Forms/Building Division/Building Permft
BUILDING PERMIT INSPECTION RECORD
PLEASE PROVIDE A MINIMUM 24-HOUR NOTICE FOR INSPECTIONS
Building Inspections 417-4815 Electrical Inspections 417-4735
Public Works Utilities 417-4831 Backflow Prevention Inspections 417-4886
IT IS UNLAWFUL TO COVER, INSULATE OR CONCEAL ANY WORK BEFORE INSPECTED AND ACCEPTED.
POST PERMIT INCONSPICUOUS LOCATION. KEEP PERMIT AND APPROVED PLANS AT JOB SITE.
Inspection Type Date Accepted By Comments
FOUNDATION:
Footings
Stemwall
Foundation Drainage/Downspouts
Piers
Post Holes(Pole Bldgs.)
PLUMBING:
Under Floor/Slab
Rough-in
Water Line Meter to Bldg)
Gas Line
Back Flow/Water
AIR SEAL:
Walls
Ceiling
FRAMING:
Joists/Girders/Under Floor
Shear Wall/Hold Downs
Walls/Roof/Ceiling
Drywall Interior Braced Panel Only)
T-Bar
INSULATION:
Slab
Wall/Floor/Ceiling
MECHANICAL:
Heat Pump/Furnace/FAU/Ducts
Rough-In
Gas Line
Wood Stove/Pellet/Chimney
Commercial Hood/Ducts
MANUFACTURED HOMES:
Footing/Slab
Blocking&Hold Downs
Skirting
PLANNING DEPT. Separate Permit#s SEPA:
Parkin /Lighting ESA:
Landscaping SHORELINE:
FINAL INSPECTIONS REQUIRED PRIOR TO OCCUPANCY/USE
Inspection Type Date Accepted By
Electrical 417-4735
Construction - R.W. PW I Engineering 417-4831
Fire 417-4653
Planning 417-4750
Building 417-4815
TITSI` .G, S For City Use
CITY OF
Permit#
WASH ] N G T o N, U. S. Date Received: -/
321 E 5th Street Date Approved
Port Angeles,WA 9836
P:360-417-4817 F:360-417-4711 RAW {� 5-
Email:permitsOcityo a.us BUILDING PERMIT AP LICATION Lo+ '#7
Project Address: ® Y
Phone: '�
Primary Contact: K .Ny"t— C � L L Email:
Name , Phone
� ► GTnc
Property Mailing Address `��� ! 0 �_ Email
Owner. w
City ^ State Zip
Name } Phone —
Contractor Address Email
Information city State Zip
Contractor License# Exp.Date:
Legal Description: Zoning: Tax Parcel# Project Value: (materials and labor)
-50 (10 -v
Residential 1Sl Commercial ❑ Industrial ❑ Public ❑
Permit Demolition ❑ Fire ❑ Repair ❑ Reroof(tear off/lay over) ❑
Classification For the following,fill out both pages of permit application:
(check New Construction EX Exterior Remodel ❑ Addition ❑ Tenant Improvement ❑
appropriate) Mechanical ❑ Plumbing ❑ Other ❑
Fire Sprinkler System Proposed Irrigation System Proposed or Proposed Bathrooms Proposed Bedrooms
or Existing? Yes ❑ No ❑ 1 Existing? Yes ❑ No ❑
In addition to standard hard copy submittals please send a PDF copy of all Stormwater plans and Engineering to
www.stormwater cit oa.us
Project Description v; S',vL
Is project in a Flood Zone: Yes ❑ No� Flood Zone Type:
If in a Flood Zone, what is the value of the structure before proposed improvement? $
I have read and completed the application and know it to be true and correct.I am authorized to apply for
this permit and understand that it is my responsibility to determine what permits are required and to
obtain permits prior to work. I understand that plan review fees are not refundable after review has
occurred. I understand that I will forfeit review fees if I withdraw the application before the permit is
issued. I understand that if the permit is not picked up/issued within 18o days of submittal,the application
will be considered abandoned and the fees will be forfeited.
Date o� "- �. Print Name � UJrA{ L Signature
Residential Structures
Existing Proposed Construction For Office Use
Area Descriptions(SQ FT) Floor area Floor area $Value new area
.Basement
First Floor
Second Floor
Covered Deck/Porch/Entry ^�
Deck(over 30"or 2'd floor) of
Garage O oO
Carport
Other(describe)
Area Totals
Commercial Structures v
Area Descriptions(SQ FT) Existing Proposed Construction For Office Use
Floor area Floor area $Value new area
Existing Structure(s)
Proposed Addition
Tenant Improvement?
Other work(describe)
Site Area Totals
Lot/Site Coverage Calculations
Lot Size(sq ft) Lot Coverage(sq ft)foot print of %Lot Coverage(Total lot cov_lot size) Max Bldg Height
all structures 18 8 Q sq ft
Site Coverage(Sq Ft of all impervious) %of Site CQ,
(total site cov_lot size)
� a
Mechanical Fixtures
Indicate how inan'y of each type of fixture to be installed or relocated as part of this project.
Air Handler Size: # Haz/Non-Haz Piping Outlets:
Appliance Exhaust Fan # Heater(Suspended,Floor,Recessed wall) #
Boiler/Compressor Size: # Heating/Cooling appliance #
repair/alteration
Evaporative Cooler(attached,not # Pellet Stove/Wood-burning/Gas #
ortable) Fireplace/Gas Stove/Gas Cook Stove/Misc.
Fuel Gas Piping #of Outlets: Ventilation Fan,single duct # 7
Furnace/Heat Pumvp/ Size: # , Ventilation System #
Forced Air Unit
Plumbing Fixtures
Indicate how many of each type of fixture to be installed or relocated
Plumbing Traps # Water Heater #
Plumbing Vent piping # Medical gas piping #of Outlets:
Water Line # Fuel gas piping #of Outlets:
Sewer Line # Industrial waste pretreatment
interceptor Grease Trap) Size
Other(describe):
T:\Forms\2015 CED Form Updates\Building&Permitting\BP\Building Permit 20150415.docx
Building Soil
Builders Foundation for Success
Builders,developers,and landscapers are adopting practices that preserve
and improve the soil on building sites. Benefits include faster planting and
vibrant plant growth for quicker sales, plus better stormwater infiltration.
Local governments are beginning to require these practices.
Why build healthy soil?
• More marketable buildings and landscapes
• Better site erosion control _ w.
• Reduced need for water and chemicals
• Less stormwater runoff, better water quality,
lower costs to comply with new regulations
• Healthy landscapes=satisfied customers
Soil "best management practices" (BMPs)include preserving site
topsoil and vegetation where possible,reducing soil compaction,and :�-
amending disturbed soils with compost to restore healthy soil functions.
These BMPs will soon be required throughout western Washington.
Home buyers are asking for them now.
` r son `
� 1
• 1
5 Steps to Building Soil
FoumiaWn for Success
Washington State's municipal stormwater permits require these soil BMPs.That requirement is taking
effect locally as towns and counties around western Washington update their stormwater codes(as required
by those permits). Some jurisdictions already require the soil BMPs—all will soon.
The good news is,it's easy,and customers want it.New home buyers say they are happy to pay more for a
healthy,easy to care for landscape—and that starts with the soil.
See www.BuildingSoll.org for state and local codes,how-to tips,and more.
step 1
Retain and protect native topsoil � ' r
At Redmond Ridge.Quadrant Homes fences and protects
existing forest as an amenity and stormwater filter.Then they
grade to 12 inches below finish grade.
and vegetation where practical. I
Plan to fence and keep equipment off these protected areas, '• ' -
to prevent compaction.Tree roots are especially sensitive,and
trees are expensive to replace. 4
p t '
i;
- •
Loosen compacted subsoil, if needed.
The next
•is to place rock pads for r••• Options where there is hardpan or compaction from construction traffic:
Once foundations are in and houses are •Scarify subsoil 4 inches deep before placing topsoil
sided,framed and .. .•.
reused soil is placed(to allow for settling to 12-inch
• Rip in the first lift of topsoil,to mix with subsoil
finish
grade). compost • _ • prevents • Rip site soils 12 inches deep,before tilling in compost to
• can proceed d 8-inch depth
The goal is to have at least 12 inches of finished uncompacted soil
depth,including at least an 8-inch depth of organic-amended topsoil.
_,,.w y "`� This will improve both stormwater infiltration and plant growth.
woo, too. compost into the existing soil.
On
breakCat-mounted rippers can compaction.or rip in the first lift of p
- .
Restore soils that are disturbed
during construction. �,� � .{;. �'
Construction requires land clearing,so plan to restore soil functions for _
better stormwater management and happier customers.
Three options to restore disturbed soils: �
•Stockpile 8�reuse good quality site topsoil,or -
•Till 2-3 inches of compost into poor site soils,or
•Bring in 8 inches of compost-amended topsoil(25-35%compost)
At Shamrock Heights,Cam West Development
Amended soils may be rdled before turf installation to reduce settling andcombines a traditional feel with innovative
still retain good porosity for stormwater infiltration and plant growth. stormwater methods. Rhigh-quality
supportsoils plus mulching .-
Download the builder's guide at www.BuildingSoil.org.
step
Mulch landscape beds after planting.
High Point uses
Mulching prevents erosion,conserves moisture,prevents weeds,
and gives plants a healthy start.Use coarse bark or wood chips—
fine bark can seal the soil.
compost-amended landscapes to
manage stormwater.
ste•
At Issaquah Protect restored soils from erosion
and re-compaction.
Blakely Port ommunitie
uses compost amended.
.
soils in landscapes for a . . product
that sells.and attracts future customers ..
ka
Prevent runoff from roads or open slopes onto amended soil areas.
Compost blankets are an approved erosion control BMP(see www.
BuildingSoil.org).Use a compost blanket for erosion control during
construction,and then just till in the compost when it's time to
landscape.
Once soils have been amended,keep vehicle traffic off to prevent ��
re-compaction.Installing gravel pads for roads and driveways early
in the project will help funnel traffic and prevent erosion violations.
Loosened,amended soil is easier to plant in,and provides much �; ' � •�.
better plant survival,preventing expensive call-backs.
w
Sellinghealthy soil
valuepro's and home buyers agree on the
Jim Berger,Construction Manager for Port Blakely Communities at Issaquah Highlands says,"These soil practices work
better than anything we've tried-plants survive the first winter,and slopes don't need to be fixed later.Using compost blankets
on slopes and compost soil amendments throughout the project not only prevents erosion right away-it gives us great
vegetation establishment,even on difficult sites."
Jeff Cox,ASLA,of Triad Associates confirms,"Placing amended soils or
stockpiling topsoils has front-end costs,but there can be long-term savings
and benefits,from healthier plant material,better growing medium,and water
quality improvements." �
Greg Rabourn,co-host of Yard Talk TV show adds,"Plants aren't cheap! a _
Replacing them costs time and money. Spending a little on the soil saves
money on water,plant replacement,and landscape chemicals.And a healthy, ,
vibrant landscape is better for resale value." b 1
q
Site planning consultant Howard Stenn notes,"Preserving areas of
undisturbed vegetation saves on stormwater detention,landscaping,and
development costs.Compost soil amendment makes for quicker
planting and faster establishment.There's no doubt these practices help
sell a project."
Jim Thompson,a Shamrock Heights homeowner says,"It adds value
w, rdustorners value a healthy,
to the home now while we live in it,and for the future when we sell.
I think it adds great value to the community too." easy-care landscape,
starts with healthy soil.
WORC
PO Box 2799
+ • + • Longview WA 98632
Get ahead
ofnew regulations
Building Soil
Foundation for Success
Learn more at
www.BuildingSoil.org
SponsoredOrganic Recycling
Council,with members from the organics
recycling industry and Washington state,county,
and local governments.
Printed on recycled paper
4.
Au- A'�Ckssj��
ANdEI.£ �
CITY OF Ow
it baste upop P M
The lssuan o this and other data shall notes
specificati
building o +cial from Vis.�+
correction o errors in said p
cher data
from preventing bu+ldin ions
from
being carri on thereunder wu,sd cn in unof
codes and clinances of this j pROVAL
/ u
ALL W UBJECT f0 FfE
Date By
0 1 0
I
sc�.le
WIW
Prescriptive Energy Code Compliance for All Climate Zones in Washington
Project Information Contact Information
This project will use the requirements of the Prescriptive Path below and incorporate the
the minimum values listed. In addition, based on the size of the structure,the appropriate
number of additional credits are checked as chosen by the permit applicant.
Authorized Representative Date
All Climate Zones
R-Value' U-Factor'
Fenestration U-Factorb n/a 0.30
Skylight LI-Factor n/a 0.50
Glazed Fenestration SHGCb'e n/a n/a
Ceiling 4Y 0.026
Wood Frame Wal l9 k 1 21 int 0.056
Mass Wall R-Value' 21/21h 0.056
Floor 309 0.029
Below Grade Wall`k 10/15/21 int+TB 0.042
Slab' R-Value& Depth 10, 2 ft n/a
*Table R402.1.1 and Table R402.1.3 Footnotes included on Page 2.
Each dwelling unit in one and two-family dwellings and townhouses, as defined in Section 101.2 of the
International Residential Code shall comply with sufficient options from Table R406.2 so as to achieve the
following minimum number of credits:
1. Small Dwelling Unit: 0.5 points
Dwelling units less than 1500 square feet in conditioned floor area with less than 300 square feet of
fenestration area. Additions to existing building that are less than 750 square feet of heated floor area.
❑ 2. Medium Dwelling Unit: 1.5 points
All dwelling units that are not included in#1 or#3, including additions over 750 square feet.
❑ 3. Large Dwelling Unit: 2.5 points
Dwelling units exceeding 5000 square feet of conditioned floor area.
Table R406.2 Summary
Option Description Credit(s)
la Efficient Building Envelope 1 a 0.5 ❑
1 b Efficient Building Envelope 1 b 1.0 ❑
1c Efficient Building Envelope 1c 2.0 ❑
2a Air Leakage Control and Efficient Ventilation 2a 0.5 ❑
2b Air Leakage Control and Efficient Ventilation 2b 1.0 ❑
2c Air Leakage Control and Efficient Ventilation 2c 1.5 ❑
3a High Efficiency HVAC 3a 0.5
31b High Efficiency HVAC 3b 1.0 ❑
3c High Efficiency HVAC 3c 2.0 ❑
3d High Efficiency HVAC 3d 1.0 ❑
4 High Efficiency HVAC Distribution System 1.0 ❑
5a Efficient Water Heating 0.5 ❑
5b Efficient Water Heating 1.5 ❑
6 Renewable Electric Energy 0.5 '1200 kwh 0.0
Total Credits 0.00
*Please refer to Table R406.2 for complete option descriptions
http://www.energy.wsu.edu/Documents/2012%2ORes%2OEnergv.pd