HomeMy WebLinkAbout09012026 City Council Presentation Data Center MoratoriumData Center Impact Mitigation: Overview and Tools Port Angeles City Council Meeting September 1, 2026 What is a Data Center? •A facility that provides critical infrastructure to power modern digital services-they house servers, storage and networking equipment;require power, cooling, and security systems to ensure continuous, reliable and safe data processing and availability. •Can be any size –from small ones that support an individual business, to a cluster of small ones in a business park, to “hyperscale” facilities 1998- Tukwila Data Center- Intergate West 17,300 sf and 33 MW DCCO Telcom Center 220,000 sf retrofit Hillsboro Oregon Definitions Simple: A facility or portion of a facility housing networked computer systems and telecommunications equipment used for remote storage, processing, and distribution of data. More detailed: “Data Center” is defined as a business or commercial activity: (1) devoted to the housing, operation, or co-location of computer and networking equipment and the handling, storage, management, processing, and backing up of digital data; (2) requiring electrical capacity in excess of 25 Megavolt-Amperes (MVA); and (3) requiring uninterruptible power supplies and associated infrastructure such as cooling systems, backup power systems, and battery storage. What is a Moratorium? How do you do one? •A moratorium is a declaration by a legislative body to temporarily pause regulatory approval of this land use category as a response to findings about community needs that additional time is needed •E.g., Moratoria in Seattle, Burien and Tukwila stop applications over 20 MVA •A moratorium provides staff and the community time to understand potential impacts and needs of this use type, and develop ways to prepare/revise appropriate codes to address these potentially unique needs and impacts •Can be effective for up to 6-months*-can be renewed with findings of fact as to necessity and a hearing •Can be declared with or without a public hearing (if without, a public hearing must be held within 60 days of adoption) * up to 1 year period with work plan that needs the longer period (see RCW 35A.63.220) Choices of other Washington Cities Current City Zoning designations as they would relate to the siting of data centers Examples of Policy Considerations Potential Concerns •Energy use •Water use •Heat •Noise •E-waste related landfill pollution •Others? Potential Benefits •Tax Revenue •Infrastructure Improvement •Jobs •Beneficial Use of Vacant Properties •Community Programs •Others? Examples of Regulatory Measures to Shape Data Center Development •Zoning Code •Zoning Map •Development Standards •Sound walls to prevent generator noise pollution •Landscaping requirements •Stormwater ponds and swales •Length/width of driveway •Impact Mitigation could include •Road improvements •Schools and housing •Water supply resiliency •Building Code •Energy Code •Energy use/density •Water Use Restrictions •Agency Reviews Examples of Work Plan Components for a Moratorium Period •Research internet data center types, physical size, power consumption, water consumption, and environmental impacts •Research power consumption needs for high-priority business sectors such as advance manufacturing and aerospace •Research the need of technology businesses located in the region •Research tax implications and opportunities •Research power availability and grid infrastructure limitations and projections •Engage with community for education, communication, feedback •Coordinate research and engagement with government agencies and businesses •Prepare report on internet data center effects on power, water, environment, jobs, and economy •Propose actions to relevant boards and commissions and ultimately, the City Council Potential Next Steps (not an exhaustive list, nor in any order) •Direct staff to prepare documents to declare a moratorium to be adopted at a future City Council meeting •Direct staff to schedule a Study Session to explore policy issues in greater depth •Request recommendations from the Planning Commission •Direct staff to study issue and provide recommendations to the City Council •Direct staff to bring forward an energy- based metric for restriction through the Utility Advisory Committee •Others? Thank you! State Law: 35A.63.220 Moratoria, interim zoning controls—Public hearing—Limitation on length. •A legislative body that adopts a moratorium or interim zoning ordinance, without holding a public hearing on the proposed moratorium or interim zoning ordinance, shall hold a public hearing on the adopted moratorium or interim zoning ordinance within at least sixty days of its adoption, whether or not the legislative body received a recommendation on the matter from the planning agency. If the legislative body does not adopt findings of fact justifying its action before this hearing, then the legislative body shall do so immediately after this public hearing. A moratorium or interim zoning ordinance adopted under this section may be effective for not longer than six months, but may be effective for up to one year if a work plan is developed for related studies providing for such a longer period. A moratorium of [or] interim zoning ordinance may be renewed for one or more six-month periods if a subsequent public hearing is held and findings of fact are made prior to each renewal. Resources and data rapidly developing evolving •Data-Centers-Fact-Sheet-3.pdf (National League of Cities) •MRSC Materials: •MRSC - How Can Local Governments Prepare for Data Centers? •MRSC - What the Data Center Boom Means for Washington Local Governments •Cultivating technology (Association of Washington Cities) •WA State Data Center Workgroup Preliminary Report 12/1/2025 [EO 25-05] •Data Center Workgroup: Preliminary Report Source: Key Considerations for Data Center Development • Bipartisan Policy Center Experiences of other jurisdictions: Quincy Data Center's additional assessed value has driven down the City of Quincy's levy rate over time. The current rate is approximately 70% less than it was in 2006 before data centers located to Quincy. As a result, Quincy's other taxpayers are generally paying significantly less in property taxes. o 2006 (before data centers): $3.12 per thousand o 2016: $1.97108 per thousand o 2025: $0.087788 per thousand Community college partnership for job training