i„N3 FOR MINOR CHANGES No.2
Date:1/15/2015
Owner: City of Port Angeles
Contract Title: 4th Street Stormwater Improvements, DR03-2009
Contractor: Jordan Excavating
Subject: Raised Pavement Reflectors
Project Manager: Jonathan Boehme
Bid Item No: A-1
®Ordered by Contracting Agency E]Changed proposed by the Contractor ❑Change in scope
Change Description:
Raised reflective pavement markers will be installed on the top of the curbs
surrounding the rain gardens. These reflectors will result in the rain garden
locations being more visible at night. Clear reflectors will be installed on the top
of curbs every 10'. Up to 350 reflectors will be installed at a cost of $7.50 per
reflector or $2625.00.
All Work,materials and measurements to be in accordance with the provisions of the original contract and/or the standards specifications
and special provisions for the type of construction involved.The payments and/or additional time specified and agreed to in this order
include every claim by the Contractor for extra payment or extension of time with respect to the work described herein,including delays to
the overall project.
Original Bid Item Amount Current Bid Item Amount Cost this Change Est.Remaining Bid Item Amount
$40,000 $40,000 $2625.00 $35,153.00
CONTRACTOR: CITY OF PORT ANGELES
Signature Signature
i
Name&Title- Name&Title
'FJ Nor D;f t"�'- ab qks
Date: Date:
41'Street Stormwater Improvements 1
Minor Change Order No. 2