SECTION 00510
AGREEMENT AND PUBLIC WORKS CONTRACT
THIS AGREEMENT and PUBLIC WORKS CONTRACT("Contract") is dated effective this
1 day of fn a _ _, 2015 and is made by and between the
City of Port Angeles, a Was ington municipal corporation ("City" or "Owner"), and JMG
Constructors, LLC, a Washington Corporation, ("Contractor").
WITNESSETH:
That WHEREAS the Owner heretofore caused to be prepared certain conditions for the construction
of
CITY HALL & PENCOM UPGRADES
Project No. GG1501
and the Contractor did on day of ,2015,file with the Owner a
proposal to construct said improvements and agreed to accept as payment therefore the sum fully
stated and set forth in the Proposal, and;
WHEREAS, the said Contract Documents fully and accurately described in terms and conditions
upon which the Contractor proposes to furnish said equipment,labor,materials,and appurtenances
and perform said work, together with the manner and time of furnishing same;
IT IS THEREFORE AGREED, first, that a copy of said Proposal and other Contract Documents
filed with the Owner, as aforesaid, does, in all particulars, become a part of the Agreement and
Contract by and between the parties hereto in all matters and things therein set forth and described;
and further,that the Owner and the Contractor hereby accept and agree to the terms and conditions of
said Contract Documents as filed as completely as if said terms,specifications,conditions,and plans
were herein set out in full.
This Contract, the Contract Documents and any supporting contract documents contain all of the
agreements of the Parties with respect to any matter covered or mentioned in this Contract and no
prior agreements or understandings shall be effective for any purpose. Terms used in this Contract
which are defined in Article 1 of the General Conditions will have the meanings described therein.
No provision of this Contract may be amended except by written agreement of the Parties. The
Contractor shall not transfer or assign, in whole or in part, any or all of its obligations and rights
hereunder without the prior written consent of the City. In the event the City consents to any such
assignment or transfer, such consent shall in no way release the Contractor from any of its
obligations or liabilities under this Contract.
4/22/2015—Addenda#2 City Hall&Pencom Upgrades
Agreement and Public Works Contract 00510-1 City Project No.GG1501
I'La"
AGREEMENT and PUBLIC WORKS CONTRACT (Project No. GG1501) - continued
Subject to the preceding sentence,this Contract shall be binding upon and inure to the benefit of the
Parties' successors in interest,heirs and assigns. The venue for any dispute related to this Contract
shall be Clallam County, Washington. Failure of the City to declare any breach or default
immediately upon occurrence thereof, or delay in taking any action in connection with, shall not
waive such breach or default. This Contract shall be governed by and interpreted in accordance with
the laws of the State of Washington. Each individual executing this Contract on behalf of the City
and Contractor represents and warrants that such individuals are duly authorized to execute this
Contract. Time is of the essence for this Contract and each and all of its provisions in which
performance is a factor. Adherence to completion dates is essential to the Contractor's performance
of this Contract. In the event of a conflict between the terms and provisions of any of the Contract
Documents,the City Manager or his or her designee shall issue an interpretation of the controlling
document, which interpretation shall be final and binding.
IN FAITH WHEREOF,witness the hand and seals of both parties hereto on the day and year in this
Agreement first above written.
6
City Hall&Pencom Upgrades 4/22/2015—Addenda#2
�3City Project No. GG 1501 00510-2 Agreement and Public Works Contract
DATED the day and year set forth above.
JMG CONSTRUCTORS, LLC CITY OF PORT ANGELES
By: By: ;
Printed Name: Printed Name:
Title: Title:
Address:
City: _
`�-`Ec> ► t ! ` 5 APPROVED AS TO FORM:
Phone Number: BY• f'
fv -731 f
CITY ATTORNEY
ATTEST:
BY: 4& VOIQ
ITY CLERK
**END OF SECTION**
F
3
4/22/2015—Addenda#2 City Hall&Pencom Upgrades
Agreement and Public Works Contract 00510-3 City Project No. GG 1501
r