HomeMy WebLinkAbout001106 Original Contract City of Port Angeles Record # 001106 y$ NET ENERGY METERING CONNECTION AGREEMENT for CUSTOMER FUEL CELL, SOLAR, WIND, or HYDROPOWER ELECTRIC GENERATING FACILITIES of 100 KILOWATTS or LESS This Net Energy Metering Connection Agreement is executed in duplicate this loth day of August 20 16 between Jodi Riverstone (hereinafter referred to as "Customer"), and the City of Port Angeles Department of Public Works and Utilities (hereinafter referred to as the City). Both parties, who may be herein further referred to collectively as "Parties" and individually as "Party", agree as follows: 1. CUSTOMER ELECTRIC GENERATING FACILITY 1.1 Customer has elected, in accordance with RCW 80.60 et seq., to operate either a net energy metering fuel cell, solar, wind or hydropower electric generating facility,with a generating capacity of not more than one hundred kilowatts, in parallel with the City's transmission and distribution facilities. This generating facility is intended to offset either part or all of the Customer's electrical requirements. 1.2 Customer's Application for Net Metered Electrical Generation, including the location of the electrical generating installation and details on the electrical generating unit(s) is hereby incorporated into this agreement as Appendix A. 1.3 The installation is identified by the City with the following designators: Transformer No. 29-BT-05 , on feeder/phase VA1206/B Customer Utility Location No. 90290 1.4 A separate agreement shall be entered into for each Customer's electrical service location(s). 1.5 The electrical generating system used by the Customer shall be located on the Customer's premises. It shall include all equipment necessary to meet applicable safety,power quality, and connection requirements established by the National Electrical Code(Articles 690 and 705), National Electrical Safety Code, the Institute of Electrical and Electronics Engineers, Underwriters Laboratories, and the City's Connection Standards, as set forth in Appendix B, which is attached hereto. 1.6 The City shall have the sole authority to determine which connection requirements set forth herein are applicable to Customer's proposed installation. 2. PAYMENT FOR NET ENERGY 2.1 The City shall measure the net electricity produced or consumed by the Customer during each billing period, in accordance with normal metering practices. PW 1201-01 Net Metering Agreement.DOC 1 of 6 3/28/01 2.2 If the electricity supplied by the City exceeds the electricity generated by the Customer and fed back to the City during the billing period, or any portion thereof, then the Customer shall be billed for the net electricity supplied by the City together with the appropriate customer charge paid by other customers of the City in the same rate class. 2.3 If the electricity generated by the Customer and distributed back to the City during the billing period, or any portion thereof, exceeds the electricity supplied by the City, then the Customer shall be: (a) billed for the appropriate customer service charge as other customers of the City in the same rate class; and (b) credited for the net excess kilowatt-hours generated during the billing period, with this kilowatt-hour credit appearing on Customer's bill for the following billing period. 2.4 At the beginning of each calendar year, any remaining unused kilowatt-hour credit accumulated by the Customer during the previous year shall be granted to the City without any compensation to the Customer. 2.5 Customer shall pay any amount owing for electric service provided by the City in accordance with applicable rates and policies. Nothing in this Section 2 shall limit City's rights under applicable Rate Schedules, Customer Service Policies, and General Provisions. 3. INTERRUPTION OR REDUCTION OF DELIVERIES 3.1 The City may require Customer to interrupt or reduce deliveries as follows: (a) when necessary in order to construct, install,maintain, repair, replace, remove, investigate, or inspect any of its equipment or part of its system; or (b) if it determines that curtailment, interruption, or reduction is necessary because of emergencies, force or compliance with prudent electrical practices. 3.2 Whenever possible, the City shall give Customer reasonable notice of the possibility that interruption or reduction of deliveries may be required. 3.3 Notwithstanding any other provision of this Agreement, if at any time the City determines that either: (a) the facility may endanger City personnel, or (b) the continued operation of Customer's facility may endanger the integrity of the City's electric system, The City shall have the right to disconnect Customer's facility from the City's electric system. Customer's facility shall remain disconnected until such time as the City is satisfied that the condition(s) referenced in(a)or(b) of this section 3.3 have been corrected. 4. CONNECTION 4.1 Customer shall deliver the excess energy to the City at the City's meter. PW 1201-01 Net Metering Agreement.DOC 2 of 6 3/28/01 4.2 Customer shall pay for designing, installing, inspecting, operating, and maintaining the electric generating facility in accordance with all applicable laws and regulations and shall comply with the City's Connection Standards set forth in Appendix B, which is attached hereto. 4.3 Customer shall pay for the City's standard watt-hour meter electrical hook-up, if not already present. 4.4 Customer shall not commence parallel operation of the generating facility until written approval of the connection facilities has been given by the City. Such approval shall not be unreasonably withheld. The City shall have the right to have representatives present at the initial testing of Customer's protective apparatus. 5. MAINTENANCE AND PERMITS 5.1 Customer shall: (a) maintain the electric generating facility and connection facilities in a safe and prudent manner and in conformance with all applicable laws and regulations including, but not limited to, the City's Connection Standards, Appendix B, and (b) obtain any governmental authorizations and permits required for the construction and operation of the electric generating facility and connection facilities, including electrical permit(s). 5.2 Customer shall reimburse the City for any and all losses, damages, claims, penalties, or liability it incurs as a result of Customer's failure to obtain or maintain any governmental authorizations and permits required for construction and operation of Customer's generating facility or failure to maintain Customer's facility as required in (a) of this Section 5. 6. ACCESS TO PREMISES 6.1 The City may enter Customer's premises or property to: (a) inspect, with prior notice, at all reasonable hours, Customer's protective devices; (b) read meter; and (c) disconnect at the City's meter or transformer, without notice, the connection facilities if, in the City's opinion, a hazardous condition exists and such immediate action is necessary to protect persons, or the City's facilities, or property of others from damage or interference caused by Customer's electric generating facilities, or lack of properly operating protective devices or inability to inspect the same. 7. INDEMNITY AND LIABILITY 7.1 The Customer assumes the risk of all damages, loss, cost and expense and agrees to indemnify the City, its successors and assigns, and its respective directors, officers, employees and agents, from and against any and all claims, losses, costs, liabilities, PW1201-01 Net Metering Agreement.DOC 3 of 6 3/28/01 damages and expenses including, but not limited to,reasonable attorney fees, resulting from or in connection with performance of the agreement or which may occur or be sustained by the City on account of any claim or action brought against the City for any reason including but not limited to loss to the electrical system of the Customer, caused by or arising out of an electrical disturbance. 7.2 Such indemnity, protection, and hold harmless includes any demand, claim, suit or judgement for damages, death or bodily injury to all persons, including officers, employees or agents, and subcontractors of either Party hereto including payment made under or in connection with any Worker's Compensation Law or under any plan for employees' disability and death benefits or property loss which may be caused or contributed to by the connection, maintenance,operation, use,presence, or removal of Customer's equipment. The only exception will be liability occasioned by the sole negligence or willful misconduct of the City or its employees acting within the scope of their employment and liability occasioned by a partial negligence of the City or its employees acting within the scope of their employment to the extent that such partial liability is fixed by a court of competent jurisdiction. 7.3 The provisions of Section 7 shall not be construed to relieve any insurer of its obligations to pay any insurance claims in accordance with the provisions of any insurance policy. 7.4 The City shall have no liability, ownership interest, control or responsibility for the Customer's Electric Generating Facility or its connection with the City's electric system, regardless of what the City knows or should know about the Customer's Electric Generating Facility or its connection. 7.5 Customer recognizes that it is waiving immunity under Washington Industrial Insurance law,Title 51 RCW, and further agrees that this indemnification clause has been mutually negotiated. This indemnification shall extend to and include attorney's fees and the costs of establishing the right of indemnification hereunder in favor of the City. 8. INSURANCE 8.1 Customer shall maintain, during the term of this Agreement, Comprehensive Personal Liability Insurance with a combined single limit in an amount equivalent to the industry standard for this type of insurance. 8.2 Such insurance shall,by endorsement to the policy or policies,provide for thirty (30) calendar days written notice to the City prior to cancellation, termination, attention, or material change of such insurance. 8.3 The City shall have the right to inspect or obtain a copy of the original policy or policies of insurance. 9. INDEPENDENT CONTRACTORS 9.1 The Parties hereto are independent contractors and shall not be deemed to be partners, joint venturers, employees, franchisees or franchisers, servants or agents of each other for any purpose whatsoever under or in connection with this Agreement. 1 PW 1201-01 Net Metering Agreement.DOC 4 of 6 3/28/01 10. GOVERNING LAW 10.1 This Agreement shall be interpreted, governed, and constructed under the laws of the State of Washington as if executed and to be performed wholly within the State of Washington. Venue of any action arising hereunder or related to this agreement shall lie in Clallam County, Washington. 11. AMENDMENTS, MODIFICATIONS OR WAIVER 11.1 Any amendments or modifications to this Agreement shall be in writing and agreed to by both Parties. The failure of any Party at any time or times to require performance of any provision hereof shall in no manner affect the right at a later time to enforce the same. No waiver by any Party of the breach of any term or covenant contained in this Agreement, whether by conduct or otherwise, shall be deemed to be construed as a further or continuing waiver of any such breach or waiver of the breach of any other term or covenant unless such waiver is in writing. 12. APPENDICES The Agreement includes the following appendices attached and incorporated by reference: Appendix A: Customer's Application for Net Metered Electrical Generation to City of Port Angeles. Appendix B: City's Connection Standards for Customer Electric Generating Facilities of 100 Kilowatts or Less. 13. NOTICES All written notices shall be directed as follows: City of Port Angeles: Electrical Engineering Manager 321 East 5`h Street P.O. Box 1150 Port Angeles, WA 98362 Customer: Jodi Riverstone Name 429 W.6th St. Address Port Angeles,WA 98362 City,State&Zip i j PW 1201-01 Net Metering Agreement.DOC 5 of 6 3/28/01 Customer notices to the City, pursuant to this Section 13, shall refer to the Service Address set forth in Appendix A. 14. TERM OF AGREEMENT This Agreement shall be in effect when signed by the Customer and the City and shall remain in effect thereafter month to month unless terminated by either Party on thirty (30) days'prior written notice in accordance with Section 13. 15. SIGNATURES IN WITNESS WHEREOF, the Parties hereto have caused two originals of this Agreement to be executed by their duly authorized representatives. This Agreement is effective as of the last date set forth below: CUSTOMER: CITY OF PORT ANGELES: 'gna e Signatu r Shailesh Shere Print name Print name Asst. Director of Power Systems Title Title 08/ 15/2016 Date Date PW 1201-01 Net Metering Agreement.DOC 6 of 6 3/28/01 It- pOPTg1 f `ham APPENDIX A Application for Net Metered Electrical Generation Thank you for your interest in establishing a renewable energy or fuel cell connection with City of Port Angeles,Electric Utility. Please note generation systems must meet certain requirements to be considered. • The project must be not more than 100 kilowatts (kW)in size. • Generation must be fueled by solar,wind,hydropower, or be a fuel cell. • Owner provides power conditioning, connection,and safety equipment. • Projects will be considered on a first come first served basis. Please complete Customer and Installer Inforination and the appropriate section for the type of generation proposed to be installed. In addition,include a one-line diagram and description of protection equipment. Please allow at least ten working days for processing your application. Questions may be directed to Electrical Engineering Manager,at telephone number(360)417-4702. Customer Information Owner Name: Jodi Riverstone Mailing Address: 429 W. 6th St., Port Angeles, WA City, State&Zip: Port Angeles Email Address: Riverstone@wavecable.com Service Address: (If different than Mailing Address) Daytime Telephone: 360-640-1559 Electric Utility Account No.: 90267-90290 Expected System Operational Date: TBD Installer Information(If different from Customer Information) Installer Name: Smart Energy Today Mailing Address: 1001 Cooper Point Rd STE 140-290 City, State&Zip: Olympia, WA 98502 Email Address: solar@smartenergytoday.net Daytime Telephone: 360-243-2799 { PW1201_02[Revised 01/2016] 1 of 2 Photovoltaic Solar System Information PV Module Manufacturer: iTEK Energy PV Module Model Number: iT275 HE solar Panel Number of Modules: 16 PV Power Rating per Module: 275 DC Watts Total Output: 4400 DC Watts Inverter Manufacturer: Blue Frog solar Inverter Model Number: APs vc500A Inverter's Power Rating(kW): .5 (AC continuous) Describe the protection equipment to be used and the physical location of the installation: Microinverters contain Auto-shutdown Installation Cost Information Estimated cost of installation: $15,600.00 Drawings Attached: ❑� one line ❑I manufacturers literature ❑� design drawings PW1201_02[Revised 01/2016] 2 of 2 NO),NVH31N NVId 311S C rrgg l laua 6991-'069(09£) 'Vivo 103ro8d ' W31SAS Z9E96 VM'S313ONV 180d jou61sap wa;sAS Ad dO1300N MNb b 1S H19 M 6Zb 9LlUL VIVO`JNIOIIno 3NO1983AIW 1GOrX3ON1133HS liews NOSVW NVA3 'S31ON 1Vd3N3O o lue;insuopl6jau3 spelap;aafad o;ullawo;snp a;ep 6uiMelp ;aayS ulul LU U' M Lu 1' j U ~ W W W W Z J Z pUp U Z N ❑ U)Z Q N Z 0 z Z ZlV W N N N o U Z O Z11 LL. hO J d U U N W U W N W ❑ Z F Q 10--f Cl) o❑Z z ❑ W W W OD 2o g 3 owowo Dob Ua w O SS= W ❑J Q3:uj J O N m U U.U U } O O U Lo 0 �s F ¢ O U` O Z w� Z Z O Z a W W W T ❑ O O U)CL U-to > a. fn 2 oww o g �Zporo =mc> wwU) Lu (o W V >a H Y OU �zw�,�^w?a 2 m wz z �wCDC� U 0 ?� W Q dna 0 a o wwwZ nwwww wa Uqa �wcY)cY) (' O O �aW ¢ ❑ I-H-H-W UzHFF- W W ZION> q�Q W Cp L) ¢¢¢ ¢ ¢¢¢ p CV Z M fn wc) z g v~iu~iv~i❑'n'>N�ai~i� w�g❑oFo - V' Q Z Q w x w'T N O a Z O vi cii iii in c{ ° W� W 'n U z0 0 O,E;cq ZO ZO Zo ?H�>?z z z z z v o 00> ~ 00 CO O(DC~7Z�YooC~7 0 <o0<w?WWWW MO O zzz F`$,z zz z D- W' Zddaa n wo W U)U)��wuU)V)� ww»za0000 ° w Q � �z❑���� w C7�amw wwww a m W �z = r' N M N M c�' N ❑ ❑ M N M WW d'M M M y Q Q,Q Q W W W W(n (n O NNN?QNNNN 0P: 8 Sz ° z y m e O wWwozo'w wmmw z e2. pw0 w F =w oOmo<p w¢m�$Ja - - mwo §z - z wo0m � 6 .g zz ao �S ^�H orc zu z> +� ,7 '^. 0 Q�zozFJ zw���+ i° a w63o ^zp �o °a 8 € as z=NOW e� m Hq-"S$zw w 5Q rcgiml A, �az�'°��8' 9 °�� �� �. $yon N- i Qoowm�ssu i N <�< z x a w n o o6a �58� - aa<o�oz zr omN gogu zzwoo �oN� Waz�arwo=oi_s�wQ�n'or°sH"w>�PgF?m�wamo¢om°Qoa�°°zg=wswawp�z�Nz�ausifz W'�w�Q=am=i� o o - &ao E. w�w�aw`a .,to u 0,1< 99wog3 .62. ou'o° uo °,¢� wwoo wwuez zFa mg, r'a rg S z a ppN�JaNpQaua oUri�+ z o°�° of �F a o�W=Qizuazw� zing 2 ufiro WJwzommw --Do �zw2,s Qin o�~�=wg�gm x s= of <z m,.-swam-zz - 3oym o auw moH 1owww~Jo ��'a u�Oo arcooWS � (n _ _�¢w� 40 ow _ o_�o�mS�am�m - muu�� W awywzwa' �g°zrwm �mw? °zCoww�WgN wa?m z�o�mo z � L QU aQ�_ �u�ci �F�w w o i�z o, z o°or zzako �m za .k ms'oiao�wma¢m� mwaui°6 - � �NR� ���s3��rcw wu� UrQ� w'o�m� r* 0 �mewwu H—.6 z,ayzloz?sw.ao.o�o 'z�°��o o ���°s Z �wV�mmozzwF�o���MzwgmsN a'w�w=i� wo oz°O 'aQ mo Uw _U az oQ`u o<wo=oz� n°oyu� wmrc�w�m� 8a �mzgi58xp > z gOf�U 5� nU /t . .Vm aQ�w�Zww aZ NON p O U� "05 rile 3F�Ui,"$nn�ifn�il-nua�ige$SaLLVO< N Z O wm 911 TT sO¢8i�a r Oa mw wz° iwNz�5O..0�zw�w= °~ o>a° . 0 / g� a o ° x zw °z OQWI a,- wz gpP.8 w zoQawO1-mwLiJJ-�0wa<a�ww6wOu ,z, 0, u Orc aFam O mw M mwF ° oC� 1 vaxipw - m Owim E�w =x0 9-o Lm< w-. m rc¢za¢ w�g°s�w 5w§ as a w�r��aQ �aw j oU4 w 05 ���wwOw?z �w oam3ii ¢wr� mQw..z U 8 �i 1,3�w.0,m°-~i� _ 66 rc¢"'°ud6zwoz ms s °n wooU rc m imazO Ozxmm aqUQ m8 4 3O m6I.wU.mm a.nyza i-°Qprc ° S < m wmzpz� zF6- 3.w poz6a 6wwwrc� a0 F O Gznt�-�yx U�wO °rci 0 f°a�wF mas03y° Sr ° SW5<zy,<099�-o 20�mz JUwLL� ywa °mm .. ro5 w°O �w mulSji¢�OKwM<<O wwm Frc mu U x FFawm aJ -TU H(MTQ�$ O �Nmw SU�mWLLLL n---w FS OM1m s wNmU wO6OO ��omu�Qi¢�mLLwN �~�1-Y z OQz� - ww uogOz aow�-'O wy OU w.w`w'a mi °6¢t¢mz°U>>xz—< 9—w2 �rz°w¢✓rOmo�oF = �wwFf �aQOwzm....wopp OmmO-w+� oo> � ��p°m0n<wmz�wazzoo���a� -a o$m��omo F� s,ro ~ a wm�w . 000w° �� ��mwswmwzw baa <'axm zzoraomwv.qrwmowwF z znzw amw¢smaw. aFzraQo�o�aN3oLLo�°,0°oW �m <a oF�x��Jz a°w w = mmo�Q�wLLmx y u°u°5 w�wNQ50- .-o oZr.Z � 3 x3oau�ww�"m�n0°°gma�woli°�S0aiwwrczom"« s � t8o w�amo�c�8o�<�z'�mw��wa�zyww�zsf�xmaw >� � osds `a uuoow4w� = > zO =oawawszwZzrc3� z„apa¢ � >ws°�< ao Wmw r� w.m�3u�rc�w��a�a�°�am��'w� °m°& NO),NVd31N qy 6S -ov9(09E) P' W31SAS Z9C9o"VM'S313`.)NV 18Od NV ol jau6isaa Ovals(S Ad dO1d008 MNb y iS H19 M 6Zb ' lnoAv-1nd NOSVW NVA3 3NO1Sd3AILl IOOf juelinsuoo A6iau3 slielaa)oafwd olu()awoIsno a;ep 6ulmela 1aa4S i W Z a' U) a) a) U 1 �a) vJ a) a) W '-'^^ vJ O a) M L N ' U W (q D aa) � co Q cr a) E � oU W Lo T- L) o X 04 Lo H a N — Q U Q 2) m O O > co w vi Q W Y OL o p U- 0 o � — OZ3 w g ~ a) U) LL p m L Z LL— t L Y M b— V/ LL N w w a Y V Q 4l H w U1 _Z C7 SZ S O J O wco 2 >- w J >W O O w V) ) << — 000 co&&& O w w 11 F-u)(j)u) c0 }___ w Z Z Z >°C? NOA NVd31N A Ess LS3 EIONV N01103NN00 W3008 Z9£B6 VM'S3130NV ldOd �au6isaQwals,(g AddOldOOdMNbb 1SH19M6Zb 3L/2/L `JNI�tOV2JONY J$aWS aNOiSdanld loor AVaaV Ad NOSVW NVA3 w luel)nsuoo A6jau3 spelaa loa(ad olul jawolsn0 ale(] 6uiMe14 laa4S E a y a J VJ C'! OD ^ N W N N 0 Z ^Q CL C W f/) � 2 _@ W t u 2 d Z U a` a` @ E T E T �Q 3 y 2 y N N Q > Q T Q T O _ 0 E N N d O H O ~ O 6 j CL L- ~ z O v O o J m f0 d T (0 Q W O O U W d' LL W Q H !n z O 0 z_ x cnw W a U) Y U Q O] W U <�/ 7 �y Z f1I LLL< U' S2 > n' O J F— J Ocr- U F w Z W Z F- a Z LLLI W > wf— � �as O U W y U W Q� O J J J Q H _ Z aaa W H U (� moaf� Q Z Ou wu. F-U)U)U 0 }WW W Q O <Z Z Z O a a U) NOA NV8BIN ��yy 6991-069109£) VMJOVI4 P' '� V431SAS 291.96 VM S3739NV 180d au6isa(]walsAS Add013008AAAVV iSH19M6ZV 9l/UL 3NII , pews, NOSVW NV�3 3NolSaanlalaor 3l`JNIS W '. luelinsuo(]A6jau3 s iela(]loa!ad olul lawolsno ale(] 6ulmei(] hays Q O N � I I U N F a x (7 0 Z p N CtU- z v O N Z ¢ O M - N U ¢ N 00 00 Eill,t` y � o. F JN>YN W W U U N> p z Z O O�QwY viM dd Y O II II d a' l0 mO gV, JU LdOQ . uuj - 1 aO 0 1: it X C>: W Y m o _ u N Nara as o Cl) co >n.> D to m N O.CL N V W N Z N N (9 Q O Z p Z U ,¢Z o Q~ F I w N C ~ II �(D U N~ molly=03 W3¢ NDU W ^ �"y <7 J wo OZ W ZF-Q 1_S NW j X(na Ol �r?j N� �~ Z<F Q I I F C F W Z- oz 3: mZ m WZmn OUOF,3a a'XO '': U ZC< �¢wIo m Ow'o rv�, <co a VU�O C I- Y � W Uam K�ir J3Q3 Z 0-0 Q U N N m d o w U a c W > Wa N 3 o N o Z o N'to ¢ lOv = Q co m O�Q II �� a W W Y> O N D U W N ¢ N Z Q a II II III it II II II N 11 II II Z W 0 ?�m m w x J W of U c f-S N W 2)X cl�'i Q Z g Ln m 0 R �~Z QF¢ It .H a, UO d' W U Z 3�wcr q m N C o w (w9 O> O¢FOapo v wZZO Up 3 xF, (n �z > If F F�a�aZ mQ�a¢ v7 p0 c w00 Ll z���11wz'mlu Q?O CD �U m,>, w-$K-U NLL. W W� >0 Il (70d U(Iw�w O W O _ o X�Oo aw a» waw W d _ >Z W aC'/(7F�I-O>LL ww ZZMo7-I FW a �g 000��u, ZoozZ-Y w 0 0 0aw0$aa¢¢o0<6 Y U U ��W a O f M M z z 2 a m Q o W of g c W t d v 3 O aD o Q¢ z �.. 0m = w .s ¢Z N Q F Qo �_.._ _._......._..._ ._._I U U Q NU�Q 11 0(7 N _ i> N0 m o N> LU � fiZi, N D U W N ¢ V7 W U v Z O O U X<A o (11 ! Z Z ~ 3:g8-,_m�� z ! ¢a o Ww F N w X N¢ N C N W M(�]m o(7Z<QmL�vi Q Q» 03Z(9w NOZ N UQI-�a II XO Z w Q ZQv0 'moo W~ o E E o W¢o>>-� L W J OWU W V z �J W NOA NVa31N ` `' o f A A a u 699roONV ` r W31SAS Z9f86 VM�S3l3NV laod S310N �au6lsap wa7SAS nd dOldOOa MNbb 1S HA M 6Zb 9l/L/L `JNIN2IVM 3Nols83nia loot pews NOSVW NVn3 ui auellnsuoo/6Jau3 sllela4 loafad olul jewolsno alea 6ulMelp PENS 3 0 v O u O � a S a \ C E 6 Z C N O a m Z Y C > n O'-U U w Y v> > O u Z j ZaW maw m H O o z o a > w Y m 00 m c 0) a v a O IZ m m m O _u c a v E n N N L y C j V �c v CL 3 v m u a a m m z u�m Y N t u c uOZ W j! -0 Y _O O Z a w -t v-O C O Za vOi m Q� t m 00 m a o p v> 3 a u O a C 'mO a W o v m 0 u oj C C v O — a Q m Q/ v Q) N M X J N 4-; N m S _ ami D a c o z_ LwCa p Gw U3OZ� 0 3 0 }i a Y LaY> mavWiH°mO 0=ag v s C CO p 0O -W t O C O u O. W m�Z)U m u m t�OC00 > Q a Z a \ C .0 I v 0c M a m w u C �o a O O nE Y X a 'D a cu ncuE W O > a F m o M Z m .. cu 7 u Ou an Y > =oFz ��o c c ^ a V; m a J o >J m 0 x a`r <u mau E o Y 5 aQw a oa 0; a� c O M Y m E 0 C Y Z O O O m Y O Ca) u O C v m a C a Y 4- m `O c v ° c m ° +' m o C 'O a a a > sN (p a Y E a a 6 M MN u v m a 0 c n �wX a. ^wx n a 3 '� � � m Y ZoCWm moCzm a r ai v o 0 m }zuw p>Zd� — 3 >_ u r maZCZ WUapOZ ip �n W U in O a�a M n.u a m t YO a s - Q a favi O� apE - Y 6 - .O O>O 6 aO 00 O v N m m ho toE o c m C -ME E 2 am Y m m N a o� as a Z i-1 N M E ci O. In Non N HAN M ggqq Aaua .: 699 t-Ob9(09£) 133HS 9' N31SAS Z9£96 VM'S313ONV iHOd NOUVOI3I03dS lau6isa4 walsRs Ad dOljood MNb b 1S H19 M 6Zb 9L111L 31nOON Ad ' 3NO1Sd3AIN IOOf 'S1N3NdtnO3pews 1 ' 1 NOSVN NVA3 W ,a.-- luellnsuoo f(61E)u3 spelap PEOM olid lawolsno alep 6wMeip )says 0 5 e E � a a I, �%oa c 0 2^` s I T_ _ NOh NV83133HS 6956-Ob9(09£) i1N W31S,'S Z9£86WOVM'S3�39NV iHOd NOI1VO13103dS WS �au6lsa(]wals/g Ad dO1d008 Mb 1S H19 M 6Zb 9ULlL 2i3183AN1 , NOSVW NVA3 W 3NOiS83nla 100r S1N3lNdinO3 , I I luellnsuoo,(6jau3 Shea@(]loafad olul jewolsno ale(] 6uIMej4 laa4S 0 0 _ u 0 U V V L� O, C 0 0 0 G U U o E ip - 68g — O O O V _ w 0 0 0 o E r. �n ti n cOtl n n s C� O o o w ry ui Z Z, O O LL s c ° Q o c o> 0 ul o a E m V a Q S m c Z o o 0 Q o 0 6 O . L i > i o n fi s x D ° E _o G Z w a ? E .l d UJ o E E 0 E 0 0 0 E E V m f o E E h E . s % n. E E E 3 c u,l `o c n E E o E o r E CJ 7 E Z L 2 a 1E E W n V 2 a O O 6 — o a < c o E < 5 2 E ___... c nR°- i I I - I I I I � I I I I — I. lay I f z ja a ZZ f a Z Z Q a Z � ❑ Q F , O a ❑ N E ❑ 3 7 = O w C ol o � � gym ❑ 3 x m N o ¢ Q F 1 z C,30 6 0 < < d z s ❑ o N F _ z 3 m .... L � ❑n 7 ? n e _ 13 13 > F pOm W 9 z 13 Z W y o 0 3 in i �iN N ❑ ❑ ❑ a u ❑ Q r ; WW a, F 3 J W 0 Z J ❑ - m m f NF Q W a N C o p :.,;: wt I < a ; f z LL N Z S IJ C a Q _ 7 W LL Q N n F P m--a' U Z E ❑ N ? ii m ❑ j z u • I S 1 g NOA NV8331VOlJWJDO N 6SS L-Ob9(09E) i1N W31SAS 29696 VM'S313ONV 180d W31SAS lau6lsap wals/g nd d01300k MND h 1S HIS M6Z6 9UlJL ie .. `JNINdin 3Nolsa3nia ioor �S1N3 Wdif103 NOSVW NVn3 luellnsuop A61au3 sllelap loafOJd olul jawolsnp alep 6ulmeJp laa4S s° � g F * { a X' w '9 Iter lz V w � i ' u S 3 a Iz ;01 r � S f ''4 1J0�PORT ApCF „�s APPENDIX B CONNECTION STANDARDS ""NKS A11� for CUSTOMER ELECTRIC GENERATING FACILITIES of not more than 100 KILOWATTS A. General This Appendix sets forth the requirements and conditions for interconnected non-utility- owned electric generation where such generation may be connected for parallel operation with the service of City of Port Angeles Electric Utility (the "City"). For purposes of this Appendix, the interconnecting entity shall be designated "Customer". B. Connection Requirements 1. Customer shall conform to all applicable National Electric Code (NEC) requirements [NEC Articles 690 and 705] and building codes, and shall obtain electrical permit(s)for the equipment installation. 2. Customer shall have a dedicated lockable disconnect device between sources of alternating-current, (i.e. between inverter(s)or other power conditioning unit(s)) and the City's distribution system. The lockable disconnect must be accessible to the City at all times and only the City's lock may be used on it. 3. Customer's over current device at the service panel shall be marked to indicate power source and connection to the City's distribution system. 4. Customer's power production control system shall comply with NEC Articles 690 and 705, Underwriters Laboratories (UL) Standard 1741, Second Edition, and the Institute of Electrical and Electronics Engineers (IEEE) Standard 1547 minimum specifications, and standards for parallel operation with the City. In particular, the: a. Power output control system shall automatically disconnect from the City's source upon loss of the City's voltage and not reconnect until the City's voltage has been restored by the City. b. Power output control system shall automatically disconnect from the City's source if Customer's voltage fluctuates beyond plus or minus 10 percent, per UL 1741. c. Power output control system shall automatically disconnect from the City's if Customer's and the City's frequency fluctuates plus or minus 2 cycles per second (Hertz). d. Inverter output distortion shall meet IEEE Standard 519. C. Safety All safety and operating procedures for joint use equipment shall be in compliance with the Occupational Safety and Health Administration (OSHA) Standard 29, CFR 1910.269, the NEC, WAC rules, the Washington Industrial Safety and Health Administration (WISHA) Standard, the City Service Requirements, and equipment manufacturer's safety and operating manuals. Net Metering-Apndx B.doe 12/19/13}